Agenda item

24/00454/BC3 - Garages Rear of 40, 42, 44 and 46 Anson Chase (Shoeburyness Ward)

Minutes:

Proposal: Erect 1no. new accessible bungalow with associated amenity space, parking and carport

Applicant: Mr Martin Berry of Southend-on-Sea City Council

Agent: Mr David Lloyd of AK Design Partnership LLP

 

Resolved:- That planning permission be GRANTED subject to the following conditions:

 

01 The development hereby permitted shall begin no later than three years from the date of this decision.

 

Reason: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.

 

02 The development shall only be undertaken in accordance with the following approved plans: 5173.A.100 Rev PL1; 5173.A.101 Rev PL1.

 

Reason: To ensure the development is carried out in accordance with the consent sought, has an acceptable design and complies with Policy DM1 of the Development Management Document (2015).

 

03 Notwithstanding the information submitted with the application, no development above ground floor slab level shall take place unless and until full details and specifications of the materials to be used for all the external surfaces of the approved dwelling at the site including facing materials, roof detail, windows, doors, fascia and soffits and the carport have been submitted to and approved in writing by the Local Planning Authority under the terms of this condition. The development must then be carried out in full accordance with the approved details before the dwelling hereby approved is first occupied.

 

Reason: In the interest of visual amenity in accordance with the National Planning Policy Framework (2023), Core Strategy (2007) Policies KP2 and CP4, Development Management Document (2015) Policies DM1 and DM3, and the advice contained within the National Design Guide (2021) and the Southend-on-Sea Design and Townscape Guide (2009).

 

04 A scheme detailing how at least 10% of the total energy needs of the development hereby approved will be supplied using on site renewable sources shall be submitted to and agreed in writing by the Local Planning Authority and implemented in full prior to the first occupation of the development under the terms of this condition. This provision shall be made for the lifetime of the development and in accordance with the agreed details.

 

Reason: In the interests of providing sustainable development in accordance with Policy KP2 of the Core Strategy (2007) and Development Management Document (2015) Policy DM2.

 

05 Prior to occupation of the development hereby approved water efficient design measures set out in Policy DM2 (iv) of the Development Management Document to limit internal water consumption to 105 litres per person per day (lpd) (110 lpd when including external water consumption), including measures of water efficient fittings, appliances and water recycling systems such as grey water and rainwater harvesting shall be installed in the development hereby approved and be retained in perpetuity thereafter.

 

Reason: In the interests of providing sustainable development in accordance with Policy KP2 of the Core Strategy (2007) and Development Management Document (2015) Policy DM2.

 

06 Hours of works associated with this consent shall be 8am - 6pm Monday to Friday, 8am - 1pm Saturday. No works shall be carried out on Sundays or Bank or Public Holidays

 

Reason: In the interests of the residential amenity of the adjoining residents and to ensure that the development complies with the National Planning Policy Framework (2023), Core Strategy (2007) Policies KP2 and CP4, Development Management Document (2015) Policies DM1 and DM3 and the advice contained within the Southend-on-Sea Design and Townscape Guide (2009).

 

07 Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (Amendment) Order 2015, or any order revising or re-enacting that Order with or without modification, no development shall be carried out on the new dwellinghouse within Schedule 2, Part 1, Classes A, B, C, D and E.

 

Reason: In the interests of the residential amenity of the adjoining residents and to ensure that the development complies with the National Planning Policy Framework (2023), Core Strategy (2007) Policies KP2 and CP4, Development Management Document (2015) Policies DM1 and DM3 and the advice contained within the Southend-on-Sea Design and Townscape Guide (2009).

 

08 The development hereby approved shall be carried out in a manner to ensure that the dwelling complies with Building Regulation part M4(2) ‘accessible and adaptable dwellings’ before it is brought into use and first occupied.

 

Reason: To ensure the residential unit hereby approved provide high quality and flexible internal layouts to meet the changing needs of residents in accordance with the Development Management Document (2015) Policy DM8 as amended by the Technical Housing Standards Policy Transition Statement (2015).

 

09 The four car parking spaces and the associated vehicular access for the spaces to access the public highway shall be provided in full accordance with the details shown on approved plan 5173.A.100 Rev PL1. The car parking space noted on the approved plan as 1 and the associated vehicular access to and from the public highway shall be provided and made available for use prior to occupation of the bungalow hereby approved and shall thereafter be permanently retained solely for the parking of vehicles and the accessing of the car parking space in connection with the occupiers of that dwelling and their visitors. The car parking space noted on the approved plan as 1 shall be fitted with an active electric vehicle charging point prior to first occupation of the dwelling. The remaining three parking spaces to the south of the proposed dwelling shall be permanently retained for public use.

 

Reason: To ensure that satisfactory off-street car parking is provided in the interests of highway safety, in accordance with the National Planning Policy Framework (2023), Core Strategy (2007) Policy CP3, Development Management Document (2015) Policy DM15 and the guidance in the Electric Vehicle Charging Infrastructure for New Development Supplementary Planning Document (2021).

 

10 No drainage infrastructure associated with the development hereby approved shall be installed until details of surface water attenuation for the site, based on Sustainable Drainage Systems principles, have been submitted to and approved in writing by the Local Planning Authority under the provisions of this condition. Any drainage infrastructure shall be installed in line with the approved details and maintained on site as approved thereafter.

 

Reason: To ensure the approved development does not increase flood risk on site or elsewhere in accordance with the National Planning Policy Framework (2023) and Core Strategy (2007) Policies KP1 and KP2.

 

11 Prior to the first occupation of the dwelling hereby approved, covered and secure cycle parking for at least one bicycle and covered and screened bin storage facilities shall be provided for the future occupiers of the dwelling and made available for use on site in line with full details (including elevations) which have previously been submitted to and approved in writing by the Local Planning Authority under the provisions of this condition. The approved facilities shall be retained for the benefit of the future users and occupiers of the approved development and their visitors for the lifetime of the development.

 

Reason: To ensure the provision of adequate cycle parking and bin storage in accordance with the National Planning Policy Framework (2023), Core Strategy (2007) Policy CP3, Development Management Document (2015) Policies DM3, DM8 and DM15 and the advice contained within the Waste Storage, Collection and Management Guide for New Developments (2019).

 

12 a) Site Characterisation: Notwithstanding the details submitted and otherwise hereby approved, no development shall take place, other than that required to carry out additional necessary investigation which in this case may include demolition and site clearance, until an investigation and risk assessment has been submitted to and approved in writing by the Local Planning Authority under the terms of this condition. The risk assessment shall assess the nature and extent of any contamination on the site whether or not it originates on the site. The investigation and risk assessment must be undertaken by competent persons and a written report of the findings must be submitted to and approved in writing by the local planning authority.

 

The report of the findings must include:

i) A survey of extent, scale and nature of contamination;

ii) An assessment of the potential risks to:

 

o Human health;

o Property (existing or proposed) including buildings, crops, livestock, pets, woodland and service lines and pipes;

o Adjoining land;

o Groundwaters and surface waters;

o Ecological systems;

o Archaeological sites and ancient monuments; and

 

iii) An appraisal of remedial options, and proposal of the preferred option(s).

 

This must be conducted by a competent person and in accordance with DEFRA and the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR 11' and the Essex Contaminated Land Consortium's 'Technical Guidance for Applicants and Developers' and is subject to the approval in writing of the Local Planning Authority.

 

(b) Remediation Scheme: Notwithstanding the details submitted and otherwise hereby approved, no development shall be undertaken, other than where necessary to carry out additional investigation, until a detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property and the natural and historical environment has been submitted to and approved in writing by the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works and site management procedures. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works. This must be conducted by a competent person and in accordance with DEFRA and the Agency's 'Model Procedures for the Management of Land Contamination, CLR 11' and the Essex Contaminated Land Consortium's 'Technical Guidance for Applicants and Developers' and is subject to the approval in writing of the Local Planning Authority.

 

(c) Implementation of Remediation Scheme: Notwithstanding the details submitted and otherwise hereby approved, no development shall be undertaken unless and until the measures set out in the detailed remediation scheme approved under part (b) of this condition have been implemented. The Local Planning Authority may give approval for the commencement of development prior to the completion of the remedial measures when it is deemed necessary to do so in order to complete the agreed remediation scheme. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works. Following completion of measures identified in the approved remediation scheme, a verification report that demonstrates the effectiveness of the remediation carried out must be produced. This must be conducted by a competent person and in accordance with DEFRA and the Environment Agency’s 'Model Procedures for the Management of Land Contamination, CLR11' and the Essex Contaminated Land Consortium's 'Technical Guidance for Applicants and Developers' and is subject to the approval in writing of the Local Planning Authority.

 

(d) Reporting of Unexpected Contamination: In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing within 7 days to the Local Planning Authority. Development must be halted on that part of the site until an assessment has been undertaken in accordance with the requirements of part (a) of this condition, and where remediation is necessary a remediation scheme, together with a timetable for its implementation, has been submitted to and approved in writing by the Local Planning Authority in accordance with the requirements of part (b) of this condition. The measures in the approved remediation scheme must then be implemented in accordance with the approved timetable. Following completion of measures identified in the approved remediation scheme a validation report must be submitted to and approved in writing by the Local Planning Authority before the development is brought into use.

 

Reason: A pre-commencement condition is justified to ensure that any contamination on site is identified and treated so that it does not harm anyone who uses the site in the future and in accordance with the National Planning Policy Framework (2023), Policies KP2 and CP4 of the Core Strategy (2007) and Policy DM14 of the Development Management Document (2015).

 

13 The development hereby permitted shall not be occupied until and unless full details of both hard and soft landscape works to be carried out at the site in association with the development have been submitted to and approved in writing by the Local Planning Authority under the terms of this condition. The approved hard landscaping works shall be completed prior to first occupation of the development and the soft landscaping works within the first planting season following first occupation of the development. The details submitted shall include, but not be limited to:

 

i. hard surfacing materials;

ii. details of the number, size and location of trees, shrubs and plants to be planted together with a planting specification;

iii details of any permeable paving or other sustainable drainage measures to be implemented;

iv. all and any means of enclosing the site;

v. existing and proposed finished levels or contours.

 

Any trees or shrubs dying, removed, being severely damaged or becoming seriously diseased within five years of planting shall be replaced with trees or shrubs of such size and species as may be agreed with the Local Planning Authority under the terms of this condition.

 

Reason: In the interests of visual amenity, the amenities of occupiers and the amenities of neighbouring occupiers, and to ensure a satisfactory standard of landscaping is implemented pursuant to Policies KP2 and CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015).

 

14 No development shall take place, including any works of demolition, unless and until a Demolition and Construction Management Plan and Strategy (to include Noise and Dust Mitigation Strategies) has been submitted to and approved in writing by the Local Planning Authority pursuant to this condition. The approved Demolition and Construction Management Plan and Strategy shall be adhered to in full throughout the construction period. The Strategy shall provide, amongst other things, for:

 

i) the parking of vehicles of site operatives and visitors,

ii) loading and unloading of plant and materials,

iii) storage of plant and materials used in constructing the development,

iv) the erection and maintenance of security hoarding,

iv) measures to control the emission of dust, dirt, mud being carried onto the road and noise during construction,

v) a scheme for recycling/disposing of waste resulting from construction works that does not allow for the burning of waste on site.

vi) a dust management plan to include mitigation and boundary particulate monitoring during demolition and construction. and

viii) details of the duration and location of any noisy activities.

 

Reason: A pre-commencement condition is justified in the interest of the residential amenity of nearby occupiers in accordance with the National Planning Policy Framework (2023), Policies KP2 and CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015).

 

Positive and Proactive Statement:

 

The Local Planning Authority has acted positively and proactively in determining this application by assessing the proposal against all material considerations, including planning policies and any representations that may have been received and subsequently determining to grant planning permission in accordance with the presumption in favour of sustainable development, as set out within the National Planning Policy Framework. The detailed analysis is set out in a report on the application prepared by officers.

 

Informatives:

 

1. Please note that the development the subject of this application is liable for a charge under the Community Infrastructure Levy (CIL) Regulations 2010 (as amended) and it is the responsibility of the landowner(s) to ensure they have fully complied with the requirements of these regulations. A failure to comply with the CIL regulations in full can result in a range of penalties. For full planning permissions, a CIL Liability Notice will be issued by the Council as soon as practicable following this decision notice. For general consents, you are required to submit a Notice of Chargeable Development (Form 5) before commencement; and upon receipt of this, the Council will issue a CIL Liability Notice including details of the chargeable amount and when this is payable. If you have not received a CIL Liability Notice by the time you intend to commence development it is imperative that you contact S106andCILAdministration@southend.gov.uk to avoid financial penalties for potential failure to comply with the CIL Regulations 2010 (as amended). If the chargeable development has already commenced, no exemption or relief can be sought in relation to the charge and a CIL Demand Notice will be issued requiring immediate payment. Further details on CIL matters can be found on the Planning Portal (www.planningportal.co.uk/info/200136/policy_and_legislation/70/community_infrastructure_levy) or the Council's website (www.southend.gov.uk/cil).

 

2. You should be aware that in cases where damage occurs during construction works to the highway in implementing this permission that Council will seek to recover the cost of repairing public highways and footpaths from any party responsible for damaging them. This includes damage carried out when implementing a planning permission or other works to buildings or land. Please take care when carrying out works on or near the public highways and footpaths in the city.

 

3. If construction works are to be considered outside of normal hours especially overnight or are expected to cause a nuisance to existing receptors it is recommended that the applicant applies for a prior consent application under section 61 of the Control of Pollution Act 1974. A consent enables the applicant to conduct the works without the worry of enforcement provided they comply with it. The applicant will have to submit details of any noisy works including type of plant and machinery to be used, proposed daily start and finish times, consultation with nearby residents and businesses and duration and time scales of the works. The applicant will need an acoustically qualified person who will be able to calculate the predicted noise levels form the operation and the impact on nearby residents and then be able to evaluate mitigation measures that can be used.

 

If the Council’s Regulatory Services become aware of any works that are highly likely to cause a nuisance, they can serve a notice under section 60 of the Control of Pollution Act 1974 to prevent this. A breach of this will represent a criminal offence.

 

The application form and guidance are available on the Southend-on-Sea City Council website. The applicant can also contact the Regulatory Services Team at Southend-on-Sea City Council for details.

Supporting documents:

 

Get the best from this site

We use simple text files called 'cookies'. Some of these cookies are essential to make our site work and others help us to improve by giving us some insight into how the site is being used. For more information, including how to turn cookies off, see more about cookies - or simply click the Continue button to use this site as normal.