Decision details

HRA Land Review Phase 4 (Lundy Close) Update

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

The Cabinet considered a report of the Deputy Chief Executive and Executive Director (Growth & Housing) providing an update on the progress of the HRA Land Review Phase (Lundy Close) and set out options to progress the development.

 

Resolved:-

 

1.    That the progress undertaken to date on HRA Land Review Phase 4 as set out in sections 3.3-3.6 to the submitted report, be noted.

 

2.    That the scheme be progressed on the basis of option 3 as set out in the report.

 

Recommended:-

 

3.    That the reduction in the associated capital budget for the project, be approved.

 

Reason for decision:

 

To update Cabinet on the progress of the HRA Land Review Phase 4 and to take forward the most appropriate option in order to the progress the scheme.

 

Other options:

 

As set out in the report

 

Note: The decisions in 1-2 above constitute an Executive Function. The decision in 3 above constitutes a Council Function.

Eligible for call-in to: Policy ad Resources Scrutiny Committee

Executive Member: Cllr Gilbert

Report author: Glyn Halksworth

Publication date: 18/09/2020

Date of decision: 15/09/2020

Decided at meeting: 15/09/2020 - Cabinet

Effective from: 26/09/2020

Accompanying Documents:

 

Get the best from this site

We use simple text files called 'cookies'. Some of these cookies are essential to make our site work and others help us to improve by giving us some insight into how the site is being used. For more information, including how to turn cookies off, see more about cookies - or simply click the Continue button to use this site as normal.