Internal Audit Report: Better Queensway Highways Scheme

Meeting: 12/10/2021 - Place Scrutiny Committee (Item 405)

405 Internal Audit Report: Better Queensway Highways Scheme pdf icon PDF 192 KB

Additional documents:

Minutes:

The Committee considered the report of the Executive Director (Finance & Resources) that presented the findings from the internal audit work in relation to the questions and concerns raised by a group of Councillors about the highways scheme element of the Better Queensway regeneration development and the options for the underpass and roundabout.  This had recently been considered by the Council’s Audit Committee at its meeting on 22nd September 2021 (Minute 359 refers).  The Scrutiny Committee also had before it a copy of the draft Minutes of that meeting.

 

The Committee debated the matter in detail and asked a number of questions which were responded to by the Leader of the Council, relevant officers and Mr Pearce, Chief Executive of Swan Housing.

 

In response to a question regarding the viability and potential costs of a highways scheme retaining an underpass in line with the 2018 highways design, the Leader of the Council undertook to re-circulate the financial details to all Councillors that had been previously provided in this regard within the next two weeks.

 

The Committee took the opportunity to thank the Head of Internal Audit for his engagement and the hard work undertaken by his team in preparing a comprehensive report.

 

Resolved:-

 

1. That the findings of the internal audit work (outlined at Section 4 of the report of the Executive Director (Finance and Resources) and reported in full at Appendix A of the submitted report), be noted and that the recommendations set out in the internal audit report at Appendix A, be endorsed.

 

2. That the recommendation in Minute 359(4) of the Audit Committee should not be agreed. Recommendation 4 was “that the powers delegated to officers by Cabinet in relation to Better Queensway regeneration project should cease (although for the avoidance of doubt powers delegated to officers in Part 3 Schedule 3 of the Constitution and the SO46 procedure in Part 4a shall continue to apply in appropriate circumstances”).

 

3. That, in accordance with Standing Order 39, the matter be referred to full Council for decision.

 

Note:

Resolution 1 above is a Scrutiny Function.

Resolution 2 above is an Executive Function.


Meeting: 22/09/2021 - Audit Committee (Item 359)

359 Internal Audit Report: Better Queensway Highways Scheme pdf icon PDF 232 KB

Additional documents:

Minutes:

The Committee received a report of the Executive Director (Finance & Resources) that presented the findings from the internal audit work in relation to the questions and concerns raised by a group of Councillors about the highways scheme element of the Better Queensway regeneration development and the options for the underpass and roundabout.

 

The Committee asked a number of questions which were responded to by the Council’s Head of Internal Audit.

 

The Committee took the opportunity to thank the Head of Internal Audit for his engagement and the hard work undertaken by his team in preparing a comprehensive report.

 

Resolved:

 

1.  That the findings of the internal audit work (outlined at section 4 of the report of the Executive Director (Finance and Resources) and reported in full at Appendix A of the submitted report) be noted and that the recommendations set out in the internal audit report at Appendix A be endorsed and that a report on progress be submitted to the Audit Committee for consideration in April 2022.

 

2.  That the report and recommendations of the Committee be referred to the Place Scrutiny Committee for consideration at its special meeting taking place on 12th October 2021.

 

3.  That the future Minutes of the meetings of the Better Queensway Programme Board be regularly submitted to The Shareholder Board for information.

 

4.  That the powers delegated to Officers by Cabinet in relation to the Better Queensway regeneration project should cease (although for the avoidance of doubt powers delegated to Officers in Part 3 Schedule 3 of the Constitution and the SO46 procedure in Part 4a shall continue to apply in appropriate circumstances).


 

Get the best from this site

We use simple text files called 'cookies'. Some of these cookies are essential to make our site work and others help us to improve by giving us some insight into how the site is being used. For more information, including how to turn cookies off, see more about cookies - or simply click the Continue button to use this site as normal.