Agenda item

18/01975/FULM - Land at Barge Pier Road, Shoeburyness (Shoeburyness Ward)

Minutes:

Proposal: Re-grading and retention of existing on-site spoil heap, erect 9 Commercial Units (Use Class B1/B8) with ancillary Trade Counter, 1 Retail Unit (unit 8) (Use Class A1) and 1 Unit (Use Class Sui Generis) for use as Vets (unit 1), layout Car Parking Spaces and Cycle Parking, construction of vehicular and pedestrian accesses from existing roundabout and layout soft landscaping.

Applicant: Garrison Developments LLP

Agent: Pomery Planning Consultants

 

Resolved:-

 

That PLANNING PERMISSION be GRANTED subject to the following conditions:

 

01 The development hereby permitted shall be begun not later than 3 years beginning with the date of this permission.

 

Reason: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.

 

02 The development hereby permitted shall be carried out in accordance with the approved plans: NGR LOC d, NGR 08, NGR 09, NGR 06a, NGR 07, NGR 57c, NGR 51c, NGR52a, NGR 53b, NGR 61, NGR 58a, NGR 59a, NGR 60a

 

Reason: To ensure that the development is carried out in accordance with the development plan.

 

03 Notwithstanding the details shown on the plans submitted and otherwise hereby approved the development hereby permitted shall not commence above a ground floor slab level unless and until details and appropriately sized samples of the materials to be used for all the external surfaces of the proposed buildings at the site, including facing materials, roof detail and windows and doors, have been submitted to and approved in writing by the local planning authority. The works must then be carried out in full accordance with the approved materials, details and specifications before the development hereby approved is brought into first use.

 

Reason: To safeguard character and appearance of the area in accordance with the National Planning Policy Framework (2019), Policies KP2 and CP4 of the Core Strategy (2007), Policies DM1 and DM3 of the Development Management Document (2015) and the Design and Townscape Guide (2009).

 

04 Notwithstanding the details shown on the plans submitted and otherwise hereby approved no development shall take place above ground floor slab level unless and until there has been submitted to and approved in writing by the Local Planning Authority a scheme of hard and soft landscaping for the site.  This shall include details of the number, size and location of the trees and shrubs to be planted together with a planting specification, details of measures to enhance biodiversity within the site; details of the treatment of all hard and soft surfaces and all means of enclosing the site.

 

All planting and biodiversity enhancements in the approved scheme shall be carried out within the first available planting season following first use of the development hereby approved.  Any shrubs dying, removed, being severely damaged or becoming seriously diseased within five years of planting shall be replaced with trees or shrubs of such size and species as may be agreed with the Local Planning Authority. Hard landscaping and means of enclosure shall be implemented in full accordance with the approved scheme prior to occupation of any part of the development hereby approved.

 

Reason: In the interests of visual amenity, biodiversity and the amenities of occupiers and to ensure a satisfactory standard of landscaping pursuant to Policies KP2 and CP4 of the Core Strategy, Policies DM1 and DM3 of the Development Management Document (2015) and the Design and Townscape Guide (2009).

 

05 The development shall not be first occupied unless and until vehicle manoeuvring areas and 111 on site car parking spaces have been provided and made available for use in full accordance with drawing NGR06a. The parking spaces shall be permanently maintained thereafter solely for the parking of occupiers of and visitors to the development.

 

Reason: To ensure that adequate car parking is provided and retained to serve the development in accordance with Policy DM15 of the Council’s Development Management Document (2015) and Policy CP3 of the Core Strategy (2007).

 

06 Notwithstanding the details shown on the plans submitted and otherwise hereby approved no development above ground floor slab level shall be undertaken unless and until full details of the secure, covered cycle parking for no less than 36 cycles have been submitted to and approved in writing by the local planning authority.  The approved cycle parking facilities shall be provided in full and made available for use for the development prior to the first use of the development hereby approved and be retained as such in perpetuity.

 

Reason: To ensure that satisfactory secure off-street bicycle parking is provided in accordance with Core Strategy (2007) Policies KP2 and CP4, Development Management Document (2015) Policy DM1, DM3 and DM15 and the guidance contained in the Design and Townscape Guide (2009).

 

07 No part of the development hereby approved shall be first occupied or brought into first use unless and until a waste management plan which includes full details of refuse and recycling storage and servicing arrangements has been submitted to and agreed in writing by the Local Planning Authority. The waste management and servicing of the development shall be carried out solely in accordance with the approved details from the first use of the development.

 

Reason:  To ensure that the development is satisfactorily serviced and that satisfactory waste management is undertaken in the interests of highway safety and visual amenity and to protect the character of the surrounding area, in accordance with Policies KP2 and CP3 of the Core Strategy (2007) and Policy DM15 of the Development Management Document (2015) and Design and Townscape Guide (2009).

 

08 None of the Individual unit hereby approved shall be first occupied or brought into first use unless and until full details of the operating and opening times of that unit have been submitted to and approved in writing by the local planning authority. Each unit shall subsequently be operated only in full accordance with the details approved under this condition.

 

Reason:  To  protect  residential  amenity  and  general  environmental quality in accordance with the National Planning Policy Framework (2019), Core  Strategy (2007)  Policies KP2  and  CP4,  and  Policies DM1 and DM3 of the Development Management Document (2015).

 

09 External lighting shall only be installed and operated in the development hereby approved in accordance with details that have previously been submitted to and approved in writing by the local planning authority.

 

Reason: In the interest of the safety and amenities of the area, and to protect the amenities of surrounding occupiers in accordance with policies  KP2 and CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015).

 

10 CCTV shall only be installed and operated in the development hereby approved in accordance with details that have previously been submitted to and approved in writing by the local planning authority.

 

Reason: To safeguard character and appearance of the area and amenities of neighbouring occupiers in accordance with Policies KP2 and CP4 of the Core Strategy (2007), Policies DM1 and DM3 of the Development Management Document (2015) and the Design and Townscape Guide (2009).

 

11 Prior to first use of the development hereby approved a scheme detailing how at least 10% of the total energy needs of the development will be supplied using on site renewable sources must be submitted to and agreed in writing  by the Local Planning Authority and implemented in full. This provision shall be made for the lifetime of the development.

 

Reason: In the interests of providing sustainable development and ensuring a high quality of design in accordance with Policy KP2 of the Core Strategy (2007) and the Design and Townscape Guide (2009).

 

12 Demolition or construction works associated with this permission shall not take place outside 08:00 hours to 18:00 hours Mondays to Fridays and 08:00hours to 13:00hours on Saturdays and at no time on Sundays or Bank Holidays.

 

Reason: In order to protect the amenities of surrounding occupiers and to protect the character the area in accordance with Policies KP2 and CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015).

 

13 Commercial refuse collection and delivery times for the development hereby approved shall not take place outside 08:00 hours to 18:00 hours Mondays to Fridays and 08:00hours to 13:00hours on Saturdays and at no time on Sundays or Bank Holidays.

 

Reason: In order to protect the amenities of surrounding occupiers and to protect the character the area in accordance with Policies KP2 and CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015).

 

14 Notwithstanding the information submitted and otherwise hereby approved and notwithstanding the provisions of Section 55(2) of the Town and Country Planning Act (1990), as amended, or any provisions amending, revoking or re-enacting that section no mezzanine floorspace shall be constructed within any unit within the approved development unless express planning permission for such works has previously been granted.

 

Reason: To enable the Local Planning Authority to regulate and control the development in the interests of amenity of neighbour properties and to ensure that sufficient parking and cycle parking is provided in accordance with the National Planning Policy Framework (2019), Policies KP2 and CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015).

 

16 The development hereby approved shall be implemented in strict accordance with the findings, recommendations and conclusions of the approved Flood Risk Assessment and Drainage Strategy undertaken by Ardent dated August 2018 reference H523-01A, including the flood resistance and resilience measures at paragraphs 6.18-6.19 of the strategy, before the development is brought into first use. The development shall thereafter be managed in accordance with the approved measures. Finished ground floor levels in the development shall be set no lower than 3.00 metres above Ordnance Datum (AOD). 

 

Reason:  To ensure the approved development is safe and does not increase flood risk elsewhere in accordance with National Planning Policy Framework (2019), Core Strategy (2007) Policies KP1, KP2 and KP3.

 

17 The development hereby approved shall be undertaken and completed in strict accordance with the findings, recommendations and conclusions of the approved Ecology Statement undertaken by D F Clark Bionomique Ltd dated 22 March 2018 reference DFCP3398, including the mitigation measures set out on pages 16-18 of the statement.

 

Reason: To ensure the development results in no adverse harm to ecology or biodiversity in accordance with the National Planning Policy Framework (2019), Core Strategy (2007) Policies KP1, KP2 and CP4.

 

18 No development above ground floor slab level shall be undertaken unless and until full details of the bird and bat boxes to be installed at the site have been submitted to and approved in writing by the local planning authority. The approved bird and bat boxes shall be provided in full prior to the first use of the development hereby approved and be retained as such in perpetuity.

 

Reason: To ensure the development results in no adverse harm to ecology or biodiversity in accordance with the National Planning Policy Framework (2019), Core Strategy (2007) Policies KP1, KP2 and CP4.

 

19 No development shall take place, until and unless a Construction Method Statement has been submitted to, and approved in writing by, the Local Planning Authority. The approved Statement shall be fully adhered to throughout the construction period. The Statement shall provide, amongst other things, for:

 

i)  the parking of vehicles of site operatives and visitors

ii)  loading and unloading of plant and materials

iii)  storage of plant and materials used in constructing the development

iv)  the erection and maintenance of security hoarding 

v)  measures to control the emission of noise, dust and dirt during construction

vi)  A scheme for recycling/disposing of waste resulting from construction works that does not allow for the burning of waste on site.

 

Reason: This pre-commencement condition is needed in the interests of visual amenity and the amenities of neighbouring occupiers pursuant to Policy CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015).

 

20 Prior to first occupation and first use of the development hereby approved, a Travel Plan including a comprehensive survey of users, targets to reduce car journeys to and from the site, identifying sustainable transport modes including cycling and modes of public transport and measures to reduce car usage shall be submitted to and agreed in writing by the local planning authority. The approved Travel Plan shall be fully implemented prior to first use of the development hereby approved and be maintained thereafter in perpetuity. For the first three years at the end of each calendar year a document setting out the monitoring of the effectiveness of the Travel Plan and setting out any proposed changes to the Plan to overcome any identified issues and timescales for doing so must be submitted to and approved in writing by the local planning authority. The agreed adjustments shall be implemented in accordance with the agreed conclusions and recommendations.

 

Reason: In the interests of sustainability, accessibility, highways efficiency and safety, residential amenity and general environmental quality in accordance with the National Planning Policy Framework (2019), Core Strategy (2007) Policies KP2, CP3 and CP4, Development Management Document (2015) Policy DM15, and Design and Townscape Guide (2009).

 

20 Decontamination

 

A.            Site Characterisation

No development other than demolition shall take place until and unless an assessment of the nature and extent of contamination has been submitted to and approved in writing by the Local Planning Authority. This assessment must be undertaken by a competent person, and shall assess any contamination on the site, whether or not it originates on the site. Moreover, it must include:

(i) a survey of the extent, scale and nature of contamination; 

(ii) an assessment of the potential risks to:  human health,  property, existing or proposed, including buildings, crops,  livestock, pets, woodland and service lines and pipes,  adjoining land,      ground waters and surface waters,  ecological systems,  archaeological sites and ancient monuments; 

 

B. Submission of Remediation Scheme

No development other than demolition shall take place until and unless a detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property and the natural and historical environment has been submitted to and approved in writing by the Local Planning Authority. The scheme must include all works to

be undertaken, proposed remediation objectives and remediation criteria, an appraisal of remedial options, and proposal of the preferred option(s), and a timetable of works and site management procedures. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. 

 

C. Implementation of Approved Remediation Scheme

The remediation scheme shall be implemented in accordance with the approved timetable of works. Within 3 months of the completion of measures identified in the approved remediation scheme, a validation report that demonstrates the effectiveness of the remediation carried out must be submitted to the Local Planning Authority. 

 

D. Reporting of Unexpected Contamination

 In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing within 7 days to the Local Planning Authority and once the Local Planning Authority has identified the part of the site affected by the unexpected contamination development must be halted on that part of the site.  An assessment must be undertaken in accordance with the requirements  of condition 1, and where remediation is necessary a remediation scheme, together with a timetable for its implementation, must be submitted to and approved in writing by the Local Planning Authority in accordance with the requirements of condition 2.   The measures in the approved remediation scheme must then be implemented in accordance with the approved timetable. Following completion of measures identified in the approved remediation scheme a validation report must be submitted to and approved in writing by the Local Planning Authority in accordance with condition 3. 

 

E. Long Term Monitoring and Maintenance

E1)No development shall take place until a monitoring and maintenance scheme to include monitoring the long-term effectiveness of the proposed remediation over a period of 5 years, and the provision of reports on the same must both be submitted to and approved in writing by the Local Planning Authority. 

 

E2) Following completion of the measures identified in that scheme and when the remediation scheme is complete, reports that demonstrate the effectiveness of the monitoring and maintenance carried out must be submitted to the Local Planning Authority. 

 

Reason: To ensure that any contamination on the site is identified and treated so that it does not harm anyone who uses the site in the future, and to ensure that the development does not cause pollution to Controlled Waters in accordance with Core Strategy (2007) policy KP2 and Policies DM1 and DM14 of the Development Management Document (2015).

 

21 No drainage infrastructure associated with this consent shall be undertaken at this site unless and until full details of the drainage infrastructure and a drainage strategy have been submitted to and approved in writing by the local planning authority. The strategy submitted shall apply the sustainable drainage principles and the sustainable drainage hierarchy. Where more sustainable methods of drainage are discounted clear evidence and reasoning for this shall be included within the strategy submitted. The approved drainage infrastructure and strategy shall be implemented in full accordance with the approved scheme prior to the first occupation of the development hereby approved and be retained as such thereafter.

 

Reason: To ensure satisfactory drainage of the site in accordance with Policy KP2 of the Core Strategy (2007) and Development Management Document (2015) Policy DM14.

 

22 No development or preliminary groundworks of any kind shall take place unless and until a written scheme of investigation for a programme of archaeological work has been submitted to and approved in writing by the local planning authority. This must include details of the suitably qualified person or organisation that will carry out the archaeological work and reasonable notification to the local planning authority when the work will be undertaken. The archaeological work and development must then be carried out in accordance with the approved scheme. A written report of the investigation and findings shall be produced, showing that the archaeological work and development has been carried out in accordance with the approved scheme and recommendations within the report carried out. Copies of the written report of the investigation and findings must be sent to Southend Borough Council.

 

Reason: A pre commencement condition is needed to avoid damage to archaeological remains on site as set out in the National Planning Policy Framework (2019), Core Strategy (2007), Policies KP2 and CP4, Development Management Document (2015) Policies DM1, Dm2 Design and Townscape Guide (2009).

 

23 Unit 1 hereby approved, as identified on plan number NGR 06a, shall only be used as a Sui Generis veterinary practice and shall not be used for any other purpose as defined on the date this application was submitted. Unit 1 shall not be used for any other purpose, including any purpose permitted under amendments to the Town and Country Planning (Use Classes) Order 1987 since the application was submitted nor any change of use permitted under the Town and Country Planning (General Permitted Development) Order 2015 (as amended) or in any provisions equivalent to those in any statutory instrument revoking and re-enacting these Orders, with or without modification.

 

Reason: To ensure the development is implemented in accordance with the permission sought and to enable the Local Planning Authority to retain control of the use of the floorspace within the Use Class specified so that occupation of the premises does not prejudice amenity and wider objectives of the planning system,  in accordance with the National Planning Policy Framework (2019), Policies KP2 and CP4 of the Southend-on-Sea Core Strategy (2007) and Policies DM1 and DM3 of the Southend-on-Sea Development Management Document (2015).

 

24 Unit 8 hereby approved, as identified on plan number NGR 06a, shall only be used for purposes falling within use class A1 as defined under the Town and Country Planning (Use Classes) Order 1987 on the date this application was submitted. Unit 8 shall not be used for any other purpose, including any purpose permitted under amendments to the Town and Country Planning (Use Classes) Order 1987 since the application was submitted nor any change of use permitted under the Town and Country Planning (General Permitted Development) Order 2015 (as amended) or in any provisions equivalent to those in any statutory instrument revoking and re-enacting these Orders, with or without modification.

 

Reason: To ensure the development is implemented in accordance with the permission sought and to enable the Local Planning Authority to retain control of the use of the floorspace within the Use Class specified so that occupation of the premises does not prejudice amenity and wider objectives of the planning system,  in accordance with the National Planning Policy Framework (2019), Policies KP2 and CP4 of the Southend-on-Sea Core Strategy (2007) and Policies DM1 and DM3 of the Southend-on-Sea Development Management Document (2015).

 

25 Units 2, 3, 4, 5, 6, 7, 9, 10 and 11 hereby approved, as identified on plan number NGR 06a, shall only be occupied for purposes falling within Use Classes B1 or B8 as defined under the Town and Country Planning (Use Classes) Order 1987 on the date this application was submitted. Units 2, 3, 4, 5, 6, 7, 9, 10 and 11 shall not be used for any other purpose, including any purpose permitted under amendments to the Town and Country Planning (Use Classes) Order 1987 since the application was submitted nor any change of use permitted under the Town and Country Planning (General Permitted Development) Order 2015 (as amended) or in any provisions equivalent to those in any statutory instrument revoking and re-enacting these Orders, with or without modification.

 

Reason: To ensure the development is implemented in accordance with the permission sought and to enable the Local Planning Authority to retain control of the use of the floorspace within the Use Class specified so that occupation of the premises does not prejudice amenity and wider objectives of the planning system, in accordance with the National Planning Policy Framework (2019), Policies KP2 and CP4 of the Southend-on-Sea Core Strategy (2007) and Policies DM1 and DM3 of the Southend-on-Sea Development Management Document (2015).

 

The Local Planning Authority has acted positively and proactively in determining this application by assessing the proposal against all material considerations, including planning policies and any representations that may have been received and subsequently determining to grant planning permission in accordance with the presumption in favour of sustainable development, as set out within the National Planning Policy Framework.  The detailed analysis is set out in a report on the application prepared by officers.

           

Informatives

             

1 You should be aware that in cases where damage occurs during construction works to the highway in implementing this permission that Council may seek to recover the cost of repairing public highways and footpaths from any party responsible for damaging them. This includes damage carried out when implementing a planning permission or other works to buildings or land. Please take care when carrying out works on or near the public highways and footpaths in the borough.

 

2 You should be aware that in cases where damage occurs during construction works to the highway in implementing this permission that Council may seek to recover the cost of repairing public highways and footpaths from any party responsible for damaging them. This includes damage carried out when implementing a planning permission or other works to buildings or land. Please take care when carrying out works on or near the public highways and footpaths in the borough.

 

3 Should the applicant require to carry out any alterations to the public highway they will be required to enter into the appropriate highway agreement

 

4 During construction and demolition there shall be no burning of waste material on site

 

5 Due to the proximity of the site to local residents a COPA (1974) sec 61 agreement with SBC will be required in order to control/mitigate construction noise and lorry movements  effectively.

 

6 Notification of intention to connect to the public sewer under S106 of the Water Industry Act Approval and consent will be required by Anglian Water, under the Water Industry Act 1991. Contact Development Services Team 0345 606 6087

 

7 The applicant is advised that any proposed advertisements could require separate advertisement consent.

 

8 The applicant is encouraged to provide electric vehicle charging points at the site in accordance with Policy DM15 which encourages their provision wherever practical and feasible.

Supporting documents:

 

Get the best from this site

We use simple text files called 'cookies'. Some of these cookies are essential to make our site work and others help us to improve by giving us some insight into how the site is being used. For more information, including how to turn cookies off, see more about cookies - or simply click the Continue button to use this site as normal.