Agenda item

20/01309/FUL - Development Land Underwood Square, Leigh-on-Sea

Minutes:

Proposal: Erect No.1 5 bedroom detached dwellinghouse, layout parking to front with associated crossover onto Underwood Square (Amended Proposal)

Applicant: Mr G Newton

Agent: Steven Kearney of SKArchitects

 

Mr Moore spoke as an objector.

 

Resolved: -

 

(a)       That the Interim Director for Planning  or Group Manager of Planning and Building Control be delegated authority to GRANT PLANNING PERMISSION subject to the following conditions and following the completion of a PLANNING AGREEMENT UNDER SECTION 106 of the Town and Country Planning Act 1990 (as amended) and any other appropriate legislation to secure the provision of

           a financial contribution of £125.58 (index linked)  to mitigate the potential disturbance to European designated sites in accordance with the Essex Coast Recreational disturbance Avoidance Mitigation Strategy or the securing of this same payment by other suitable means.

 

(b)       That the Interim Director of Planning or the Group Manager (Planning & Building Control) be authorised to determine the application upon completion of the above requirement, so long as planning permission when granted and, where it is used, the obligation when executed, accords with the details set out in the report submitted and the conditions listed below:

 

01 The development hereby permitted shall begin not later than three years of the date of this decision

 

Reason: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990

 

02 The development hereby permitted shall be carried out in accordance with the following approved plans 385-P800A, 385-P801, 385-P802, 385-P803, 385-P804

Reason: To ensure that the development is carried out in accordance with the Development Plan.

 

03 Prior to its occupation the materials for the external surfaces of the dwellings hereby approved shall be as set out on plan reference 385-P801 or any other details that have previously been submitted to and approved in writing by the local planning authority.

 

Reason: To safeguard the visual amenities of the area, in accordance with the National Planning Policy Framework (2019) Core Strategy (2007) policy KP2 and CP4, Development Management Document (2015) Policy DM1 and advice contained within the Southend Design and Townscape Guide (2009).  

 

?

04 The first floor and second floor windows in the north and south elevations of the approved dwelling shall only be glazed in obscure glass (the glass to be obscure to at least Level 4 on the Pilkington Levels of Privacy, or such equivalent that has been previously submitted to and agreed in writing by the local planning authority) and fixed shut up to a height of not less than 1.7m above first floor level before the occupation of the dwellings hereby approved and shall be retained as such in perpetuity.  In the case of multiple or double glazed units at least one layer of glass in the relevant units shall be glazed in obscure glass to at least Level 4.

 

Reason:  To protect the privacy and environment of people in proposed and neighbouring residential properties, in accordance with the National Planning Policy Framework (2019), Core Strategy (2007) policy CP4, Development Management Document  (2015) policy DM1, and advice contained within the Design and Townscape Guide (2009).

 

05 The hard and soft landscaping and boundary treatments at the site shall be carried out in full accordance with the proposed landscaping scheme including street tree planting as shown on plans ref 385-P801 and 385-P802 prior to occupation of the dwelling hereby approved, or any other details that have previously been submitted to and approved in writing by the local planning authority. Any trees or shrubs dying, removed, being severely damaged or becoming seriously diseased within five years of planting shall be replaced with trees or shrubs of such size and species as may be agreed with the Local Planning Authority.

 

Reason: In the interests of visual amenity of the area and the amenities of occupiers and to ensure a satisfactory standard of landscaping pursuant to Policy DM1 of the Development Management Document (2015) and Policy CP4 of the Core Strategy (2007).

 

06 No drainage infrastructure associated with this development shall be undertaken until details of the design implementation; maintenance and management of a scheme for surface water drainage works (incorporating Sustainable Urban Drainage (SuDs) Principles) have been submitted to and approved by the local planning authority. The approved scheme shall be implemented,  in accordance with the approved details before the development is occupied or brought into use and be maintained as such thereafter in perpetuity.

 

Reason: To prevent flooding by ensuring the satisfactory storage and disposal of surface water from the site for the lifetime of the development and to prevent environmental and amenity problems arising from flooding in accordance with the National Planning Policy Framework (2019), Policy KP2 and CP4 of the Core Strategy (2007) and  Policy DM2 of the Development Management Document  (2015).

 

?

07 Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (as amended), or any Order or Act of Parliament revoking and re-enacting that Order with or without modification, no extensions or detached buildings shall be erected at the development hereby approved specified within Schedule 2, Part 1, Classes A, B, D, E and F of the Town and Country Planning (General Permitted Development) Order 2015 without the receipt of express planning permission in writing from the Local Planning Authority.

 

Reason:  To enable the Local Planning Authority to regulate and control development in the interest of the amenity of neighbouring properties and to safeguard the character of the area in accordance the National Planning Policy Framework (2019), Core Strategy (2007) Policies KP2 and CP4, Development Management Document (2015) Policy DM1 and the Southend Design and Townscape Guide (2009).

 

08 The two car parking spaces and the associated vehicular access for the spaces to access the public highway, shown on approved plan 385-P801 shall be provided and made available for use at the site prior to the first occupation of the dwelling hereby approved. The car parking spaces and the associated vehicular access to and from the public highway shall thereafter be permanently retained solely for the parking of vehicles and the accessing of the car parking spaces in connection with the occupiers of the dwelling hereby approved and their visitors.

 

Reason: To ensure that satisfactory off-street car parking is provided in the interests of residential amenity and highways efficiency and safety, in accordance with the National Planning Policy Framework (2019), Core Strategy (2007) policy KP2, Development Management Document (2015) policy DM15 and the Southend Design and Townscape Guide (2009). 

 

09 The tree and tree root protection measures as set out in Sections 3 and 4 of the submitted Arboricultural Impact Assessment and Method Statement by Owen Allpress reference 1971 Rev-02 dated 20/09/20 and associated Tree Protection Plan reference 1974-02-P1 dated 20/09/20, Ground Protection Plan reference 1953-02-P1 dated 21/09/20, Cellular Confinement Plan reference 1953-02-P2 dated 25/05/20 and Tree Works Plan reference 1935-02-P3 dated 25/05/20 in relation to the trees identified as T1-T10 in this statement including the mitigation measures in relation to construction within the root protection areas of the trees denoted as T8, T9 and T10, shall be implemented in full prior to commencement of the development and be retained throughout the construction phase of the development. Implementation of the development shall be undertaken only in full accordance with British Standard 3998 and British Standard 5837 including supervision of works by a qualified arboriculturalist. The tree works to trees identified as T8 and T9 shall be restricted to that set out in Section 3.4 of the above report.

 

Reason: A condition is justified to ensure the trees on and close to the site are adequately protected during building works in the interests of visual amenity and in accordance with Core Strategy (2007) policies KP2 and CP4, Development Management Document (2015) policy DM1 and advice contained within the Southend Design and Townscape Guide (2009).

 

 

10 Prior to occupation of the dwelling hereby approved, appropriate water efficient design measures as set out in Policy DM2 (iv) of the Development Management Document to limit internal water consumption to not more than 105 litres per person per day (lpd) (110 lpd when including external  water  consumption), to include measures of water efficient fittings, appliances and water recycling systems such as grey water and rainwater harvesting shall be implemented for the development and thereafter retained in perpetuity.

 

Reason: To minimise the environmental impact of the development through efficient use of water in accordance with the National Planning Policy Framework (2019), Core Strategy (2007) Policy KP2, Development Management Document (2015) Policy DM2 and advice contained within the Southend Design and Townscape Guide (2009).

 

11 A scheme detailing how at least 10% of the total energy needs of the development will be supplied using on site renewable sources shall be submitted to, agreed in writing by the Local Planning Authority and implemented in full in accordance with the approved details prior to the first occupation of the dwelling hereby approved. This provision shall be made for the lifetime of the development.

 

Reason: To minimise the environmental impact of the development through efficient use of resources and better use of sustainable and renewable resources in accordance with the National Planning Policy Framework (2019), Core Strategy (2007) policy KP2 and CP4, Development Management Document (2015) policy DM2 and the Southend Design and Townscape Guide(2009).

 

12 The development hereby approved shall be carried out in a manner to ensure the dwellinghouse complies with building regulation M4 (2) ‘accessible and adaptable dwellings’ before it is occupied.

 

Reason: To ensure the residential unit hereby approved provides a high quality and flexible internal layout to meet the changing needs of residents in accordance with National Planning Policy Framework (2019), Core Strategy (2007) policy KP2, Development Management Document (2015) policy DM8 and the advice contained in the Southend Design and Townscape Guide (2009).

 

13 The development hereby approved shall be carried out in full accordance with the recommendation set out in table 4.1 and Section 5 of the submitted Ecological Appraisal by The Ecology Consultancy version 3.0 dated 21.09.20 and plan reference 385-P803 showing proposed habitat measures.

 

Reason: A condition is justified to ensure any protected species and habitats utilising the site are adequately protected during building works in accordance with the National Planning Policy Framework (2019), Core Strategy (2007) policy KP2, Development Management Document (2015) policy DM2.

 

14 The construction management of the site shall be carried out in full accordance with the submitted Construction Method Statement by SKArchitects reference 385-08-16 Rev A and plan reference 385-P805 showing the proposed site layout plan during construction.

 

Reason: A condition is justified in the interests of visual amenity and the amenities of neighbours pursuant to Policy CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015).

 

15 Before it is occupied the finished levels at the site shall be as set out on plan reference 385-P804. 

 

Reason: A condition is required to safeguard the visual amenities of the site and wider area as set out in Core Strategy (2007) Policies KP2 and CP4, Development Management Document (2015) Policies DM1 and DM3 and the advice contained within the Southend Design and Townscape Guide (2009).

 

16 Construction Hours for the development hereby approved shall be restricted to 8am – 6pm Monday to Friday, 8am - 1pm Saturday and not at all on Sundays or Bank Holidays.

 

Reason: In the interests of visual amenity and the amenities of neighbours and to ensure a satisfactory standard of landscaping pursuant to Policy CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015).

 

17 No external lighting shall be installed on the rear elevations of the dwellings hereby approved other than in accordance with details that have previously been submitted to and approved in writing by the local planning authority.

 

Reason: A condition is justified to ensure any protected species and habitats utilising the site are adequately protected in accordance with the National Planning Policy Framework (2019), Core Strategy (2007) policy KP2, Development Management Document (2015) policy DM2.

 

(c)        In the event that the planning obligation or other means of securing the financial contribution referred to in part (a) above has not been completed by 5th November 2020 or an extension of this time as may be agreed, the Interim Director of Planning or Group Manager Planning & Building Control be authorised to refuse planning permission for the application on the grounds that the development would not provide adequate mitigation for the potential disturbance to European designated site, contrary to National and Local planning policy. 

 

Informatives:

 

01 Please note that the development the subject of this application is liable for a charge under the Community Infrastructure Levy (CIL) Regulations 2010 (as amended) and it is the responsibility of the landowner(s) to ensure they have fully complied with the requirements of these regulations. A failure to comply with the CIL regulations in full can result in a range of penalties. For full planning permissions, a CIL Liability Notice will be issued by the Council as soon as practicable following this decision notice. For general consents, you are required to submit a Notice of Chargeable Development (Form 5) before commencement; and upon receipt of this, the Council will issue a CIL Liability Notice including details of the chargeable amount and when this is payable. If you have not received a CIL Liability Notice by the time you intend to commence development it is imperative that you contact S106andCILAdministration@southend.gov.uk to avoid financial penalties for potential failure to comply with the CIL Regulations 2010 (as amended).

 

?

02 You should be aware that in cases where damage occurs during construction works to the highway in implementing this permission that Council may seek to recover the cost of repairing public highways and footpaths from any party responsible for damaging them. This includes damage carried out when implementing a planning permission or other works to buildings or land. Please take care when carrying out works on or near the public highways and footpaths in the Borough.

 

03 The applicant is reminded that they are required to adhere to the Conservation (Natural Habitats &c.) (Amendment) Regulations 2007 and the Wildlife and Countryside Act (1981) in relation to development works close to protected species including badgers and bats. A Protected Species Licence may be required. 

 

04 The applicant is advised that the appropriate highways licences should be obtained prior to the commencement of the development.

 

The Local Planning Authority has acted positively and proactively in determining this application by assessing the proposal against all material considerations, including planning policies and any representations that may have been received and subsequently determining to grant planning permission in accordance with the presumption in favour of sustainable development, as set out within the National Planning Policy Framework.  The detailed analysis is set out in a report on the application prepared by officers.

 

 

 

 

 

Supporting documents:

 

Get the best from this site

We use simple text files called 'cookies'. Some of these cookies are essential to make our site work and others help us to improve by giving us some insight into how the site is being used. For more information, including how to turn cookies off, see more about cookies - or simply click the Continue button to use this site as normal.