21/02089/AMDT - Former 51 Chalkwell Avenue, Westcliff-on-Sea (Chalkwell Ward)

Minutes:

Proposal: Application to vary condition 02 (Approved Plans) replace plan numbers 001 Ground Floor and site Plan, 002 First Floor Plan, 003 Second Floor Plan, 004 West Elevation, 005 South Elevation, 006 North Elevation, 007 East Elevation , 008 Roof Plan with plan numbers Location Plan, 002 (18.01.2022), 003 (18.01.2022), 004 (18.01.2022), 005 (18.01.2022), 006 (18.01.2022), 007 (18.02.2022), 008 (18.01.2022), 0011 (18.01.2022), 0012 (18.01.2022) - adjustment in the reduction footprint and adjustment of the internal plans and elevations necessitated by updated survey information (Minor Material Amendment of Planning Permission 20/02224/FUL dated 2.6.2021)

Applicant: Herald Build Limited

Agent: iArch Consulting

 

Mrs Ellman, a local resident, spoke as an objector to the application.  Mr Wislocki, responded on behalf of the applicant.

 

Resolved:-

 

That planning permission be GRANTED subject to the following conditions:

 

01 The development hereby permitted shall begin not later than 2nd June 2024.

 

Reason: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990

 

02 The development hereby permitted shall be carried out in accordance with the following approved plans Location Plan, 002 (18.01.2022), 003 (18.01.2022), 004 (18.01.2022), 005 (18.01.2022), 006 (18.01.2022), 007 (18.02.2022), 008 (18.01.2022), 0011 (18.01.2022), 0012 (18.01.2022), Section Detail

 

Reason: To ensure that the development is carried out in accordance with the Development Plan.

 

03 Notwithstanding the details shown on the plans submitted and otherwise hereby approved, no construction works other than demolition and construction up to ground floor slab level shall take place unless and until full product details of the materials to be used on all the external elevations, including walls, bays and balconies, roof, eaves and roof terraces, windows and doors, entrance glazing and porch, fascia and soffits, balcony balustrades and privacy screen, bin and cycle stores, rainwater goods and boundaries have been submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details before it is brought into first use.

 

Reason: To safeguard the visual amenities of the area, in accordance with the National Planning Policy Framework (2021) Core Strategy (2007) policies KP2 and CP4, Development Management Document (2015) Policy DM1 and advice contained within the Southend Design and Townscape Guide (2009).  

 

04 Notwithstanding the details shown on the plans submitted and otherwise hereby approved, no construction works above ground floor slab level shall take place unless and until full detailed design drawings and cross sections of the main entrance and porch and entrance porch to units 2 and 3, projecting bays and balconies including balustrade details, windows and doors including reveals and framing and fixing of Juliette balconies, projecting eaves detail including soffits, flat roof ridge edge detail, dormer detail to north elevation,  tile hanging and brick decoration and any alterations to the existing boundaries to Kings Road and Chalkwell Avenue, at a scale of 1:20 or 1:10 as appropriate have first been submitted to and agreed in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details before it is brought into use.

 

Reason: To safeguard the visual amenities of the area, in accordance with the National Planning Policy Framework (2021) Core Strategy (2007) policy KP2 and CP4, Development Management Document (2015) Policy DM1 and advice contained within the Southend Design and Townscape Guide (2009).  

 

05 Prior to the occupation of the development hereby approved an obscure glazed  privacy screen (the glass to be obscure to at least Level 4 on the Pilkington Levels of Privacy, or such equivalent as may be agreed in writing with the local planning authority) of not less than 1.7m high above terrace level shall be fitted to the south side of the 2nd floor terrace to unit 9  and to the south side of the 2nd floor terrace to unit 8 for a length of 2m measured back from the rear elevation of unit 8 in accordance with details and specifications that have previously been submitted to and approved in writing by the Local Planning Authority. The screen shall be retained for the lifetime of the development in accordance with the approved details.

 

Reason: To protect the privacy and environment of people in new and neighbouring residential properties, in accordance with the National Planning Policy Framework (2021), Core Strategy (2007) policy CP4, Development Management Document (2015) policy DM1, and advice contained within the Design and Townscape Guide (2009).

 

06 Notwithstanding the details shown on the plans submitted and otherwise hereby approved, no construction works other than demolition and construction up to ground floor slab level of the existing building shall take place until full details of both hard and soft landscape works to be carried out at the site have been submitted to and approved in writing by the Local Planning Authority. The approved hard landscaping works shall be carried out prior to first occupation of the development and the soft landscaping works within the first planting season following first occupation of the development, unless otherwise agreed in writing by the Local Planning Authority. The details submitted shall include, but not limited to:-

 

i) Proposed finished site levels or contours; 

ii) Means of enclosure, of the site including any gates or boundary walls and fencing; 

iii) hard surfacing materials; 

iv) full details of any structures (e.g. benches, planters, loggias, lighting etc.).;

v) full details of the number, size and location of the trees, shrubs and plants to be retained and planted together with a planting specification and tree management plan.

vi) details of measures to enhance biodiversity within the site.

 

Any trees or shrubs dying, removed, being severely damaged or becoming seriously diseased within five years of planting shall be replaced with trees or shrubs of such size and species as may be agreed with the Local Planning Authority.

 

Reason: In the interests of the visual amenity of the area and the amenities of occupiers and to ensure a satisfactory standard of landscaping pursuant to Policy DM1 of the Development Management Document (2015) and Policy CP4 of the Core Strategy (2007)

 

07 The tree and tree root protection measures as set out in Tree Protection Plan Rev 3 dated 20.01.2022 and Appendix 3 of the Arboricultural Report Rev 03 by Andrew Day Arboricultural Consultancy Ltd dated 20.01.22  in relation to the trees identified as T2, T3, T4, T7, T8 and T9 in this statement including the mitigation measures in relation to construction within their root protection areas shall be implemented in full prior to commencement of the development and shall be retained throughout the construction phase of the development hereby approved. Implementation of the development shall be undertaken only in full accordance with British Standard 3998 and British Standard 5837 including supervision of works by a qualified arboriculturalist.

 

Reason: A pre-commencement condition is justified to ensure the trees on and close to the site are adequately protected during building works in the interests of visual amenity and in accordance with Core Strategy (2007) policies KP2 and CP4, Development Management Document (2015) policy DM1 and advice contained within the Southend Design and Townscape Guide (2009).

 

08 The 9 car parking spaces, each with associated electric vehicle charging points, the associated new vehicular access for these spaces to access the public highway on Kings Road and the reinstatement of the redundant crossover on Chalkwell Avenue back to planted verge, as shown on approved plan 012 (18.01.2022) shall be provided and made available for use prior to the first occupation of the dwellings hereby approved. The car parking spaces and the associated vehicular access to and from the public highway shall thereafter be permanently retained solely for the parking of vehicles and the accessing of the car parking spaces in connection with the occupiers of the dwelling hereby approved and their visitors.

 

Reason: To ensure that satisfactory off-street car parking is provided in the interests of residential amenity and highways efficiency and safety, in accordance with the National Planning Policy Framework (2021), Core Strategy (2007) policy KP2, Development Management Document (2015) policy DM15 and the Southend Design and Townscape Guide (2009). 

 

09 The development hereby approved shall not be occupied or brought into use until and unless the refuse and recycling storage and cycle storage facilities are provided and made available for use by the occupiers in full accordance with the details shown on approved drawings number 012 (18.01.2022) and 010 (18.01.2022) or any other details that have been previously agreed in writing by the Local Planning Authority under the terms of this condition. The refuse and recycling facilities shall be permanently retained as such thereafter. 

 

Reason: To ensure that adequate refuse and recycling storage and secure cycle parking is provided and retained to serve the development in accordance with Policy CP3 of the Core Strategy (2007) and Policy DM15 of the Development Management Document (2015).

 

10 A scheme detailing how at least 10% of the total energy needs of the development will be supplied using on site renewable sources shall be submitted to, agreed in writing by the Local Planning Authority and implemented in full in accordance with the approved details prior to the first occupation of the development hereby approved. This provision shall be made for the lifetime of the development.

 

Reason: To minimise the environmental impact of the development through efficient use of resources and better use of sustainable and renewable resources in accordance with the National Planning Policy Framework (2021), Core Strategy (2007) policy KP2 and CP4, Development Management Document (2015) policy DM2 and the Southend Design and Townscape Guide (2009).

 

11 Prior to occupation of the development hereby approved, appropriate water efficient design measures as set out in Policy DM2 (iv) of the Development Management Document to limit internal water consumption to 105 litres per person per day (lpd) (110 lpd when including external water consumption), to include measures of water efficient fittings, appliances and water recycling systems such as grey water and rainwater harvesting shall be implemented for the whole development and retained in perpetuity.

 

Reason: To minimise the environmental impact of the development through efficient use of water in accordance with the National Planning Policy Framework (2021), Core Strategy (2007) Policy KP2, Development Management Document (2015) Policy DM2 and Design and Townscape Guide (2009).

 

12 The development hereby approved shall be carried out in a manner to ensure the flats comply with building regulation M4 (2) ‘accessible and adaptable dwellings’ before they are occupied.

 

Reason: To ensure the residential units hereby approved provides a high quality and flexible internal layout to meet the changing needs of residents in accordance with National Planning Policy Framework (2021), Core Strategy (2007) policy KP2, Development Management Document (2015) policy DM8 and the advice contained in the Southend Design and Townscape Guide.

 

13 No drainage infrastructure, including earthworks, associated with this development hereby approved shall be undertaken until details of the design implementation; maintenance and management of a scheme for surface water drainage works (incorporating Sustainable Urban Drainage (SuDs) Principles) have been submitted to and approved in writing by the Local Planning Authority. The approved scheme shall be implemented in accordance with the approved details before the development is occupied or brought into use and shall be maintained as such thereafter in perpetuity.

 

Reason: To prevent flooding by ensuring the satisfactory storage and disposal of surface water from the site for the lifetime of the development and to prevent environmental and amenity problems arising from flooding in accordance with the National Planning Policy Framework (2021), Policy KP2 and CP4 of the Core Strategy (2007) and Policy DM2 of the Development Management Document (2015).

 

14 No development above ground level shall be undertaken unless and until details of existing and proposed site levels at and surrounding the site have been submitted to and approved in writing by the local planning authority. The development shall be undertaken and completed at the levels indicated on the approved drawing. 

 

Reason: In the interests of the residential amenity of adjoining residents and the character and appearance of the area and to ensure that the development complies with the National Planning Policy Framework (2021), Core Strategy (2007) Policies KP2 and CP4, Development Management Document (2015) Policies DM1 and DM3 and the Design and Townscape Guide (2009).

 

15 Construction Hours for the development hereby approved shall be restricted to 8am – 6pm Monday to Friday, 8am - 1pm Saturday and not at all on Sundays or Bank Holidays.

 

Reason: In the interests of the amenities of neighbours pursuant to Policy CP4 of the Core Strategy (2007) and Policy DM1 of the Development Management Document (2015).

 

16 The development hereby approved shall be undertaken in full accordance with the submitted Construction Method Plan Rev 2 dated 17.01.2022 or any other Construction Method Plan which has been previously submitted to and approved in writing by, the Local Planning Authority. This plan shall be fully adhered to throughout the construction period of the development.

 

Reason: This condition is needed in the interests of visual amenity and the amenities of neighbouring occupiers pursuant to Policy CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document 2015).

 

Informatives:

 

01 Please note that the development the subject of this application is liable for a charge under the Community Infrastructure Levy (CIL) Regulations 2010 (as amended) and it is the responsibility of the landowner(s) to ensure they have fully complied with the requirements of these regulations. A failure to comply with the CIL regulations in full can result in a range of penalties. For full planning permissions, a CIL Liability Notice will be issued by the Council as soon as practicable following this decision notice. For general consents, you are required to submit a Notice of Chargeable Development (Form 5) before commencement; and upon receipt of this, the Council will issue a CIL Liability Notice including details of the chargeable amount and when this is payable. If you have not received a CIL Liability Notice by the time you intend to commence development it is imperative that you contact S106andCILAdministration@southend.gov.uk to avoid financial penalties for potential failure to comply with the CIL Regulations 2010 (as amended). If the chargeable development has already commenced, no exemption or relief can be sought in relation to the charge and a CIL Demand Notice will be issued requiring immediate payment. Further details on CIL matters can be found on the Planning Portal (www.planningportal.co.uk/info/200136/policy_and_legislation/70/community_infrastructure_levy) or the Council's website (www.southend.gov.uk/cil).  

 

02 You should be aware that in cases where damage occurs during construction works to the highway in implementing this permission that Council may seek to recover the cost of repairing public highways and footpaths from any party responsible for damaging them. This includes damage carried out when implementing a planning permission or other works to buildings or land. Please take care when carrying out works on or near the public highways and footpaths in the Borough.

 

03 The applicant is advised that the appropriate highways licences should be obtained prior to the commencement of the development. The applicant is advised to contact the Councils Highways Officer martinwarren@southend.gov.uk to arrange the reinstatement of the crossover and verge on the Chalkwell Avenue frontage which must be carried out by the Councils appointed contractor. 

 

 

The Local Planning Authority has acted positively and proactively in determining this application by identifying matters of concern within the application (as originally submitted) and negotiating, with the Applicant, acceptable amendments to the proposal to address those concerns.  As a result, the Local Planning Authority has been able to grant planning permission for an acceptable proposal, in accordance with the presumption in favour of sustainable development, as set out within the National Planning Policy Framework.  The detailed analysis is set out in a report on the application prepared by officers.

Supporting documents:

 

Get the best from this site

We use simple text files called 'cookies'. Some of these cookies are essential to make our site work and others help us to improve by giving us some insight into how the site is being used. For more information, including how to turn cookies off, see more about cookies - or simply click the Continue button to use this site as normal.