Agenda item

22/00299/FUL - 54 The Ridgeway, Westcliff-on-Sea (Chalkwell Ward)

Minutes:

Proposal: Erect replacement outbuilding at rear incorporating bike store, relocate existing office space into outbuilding and form additional floorspace to shop and replace existing steps to side with ramp.

Applicant: Mr Mehmet Hassain

Agent: Mr Colin Stone of Stone me Design Ltd

 

Resolved:

 

PLANNING PERMISSION GRANTED subject to the following conditions:

 

1 The development hereby permitted shall begin no later than three years of the date of this decision.

 

Reason: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990

 

2 The development hereby permitted shall be carried out in accordance with the following approved plans: 1705-15a; 1705-16a

 

Reason: To ensure that the development is carried out in accordance with the Development Plan.

 

3 Before the development hereby approved is first used the materials used on the external surfaces of the development must match those used on the external surfaces of the existing building. This applies unless differences are shown on submitted plans.

 

Reason: In the interests of visual amenity and to ensure that the appearance of the building makes a positive contribution to the character and appearance of the area. This is as set out in the National Planning Policy Framework (2021), Core Strategy (2007) Policy KP2 and CP4, Development Management Document (2015) Policy DM1, and advice contained in the Southend-on Sea Design and Townscape Guide (2009).

 

4 The dry storage area of the outbuilding hereby permitted shall not be used at any time other than for purposes wholly ancillary to the commercial operation of the ground floor business unit known as 54 The Ridgeway.

 

Reason: In the interests of the residential amenity of the adjoining residents and to ensure that the development complies with the National Planning Policy Framework (2021), Core Strategy (2007) Policies KP2 and CP4, Development Management Document (2015) policies DM1 and DM3 and The Southend-on-Sea Design and Townscape Guide (2009).

 

5 Before any external lighting is installed in association with the outbuilding hereby permitted details of its location, design and specification shall have been submitted to and approved in writing by the Local Planning Authority. The lighting shall be installed solely in accordance with the approved details.

 

Reason: In the interests of the amenities of the area and nearby residents, in accordance with Policies DM1 and DM3 of the Development Management Document (2015) and Policies KP2 and CP4 of the Core Strategy (2007).

 

6 No plant equipment or machinery shall be installed or operated at the site unless a noise impact assessment (conducted out by a competent person) has previously been carried out, submitted to and approved in writing by the Local Planning Authority.

 

The assessment must be made using the appropriate standards and methodology for the noise sources and the relevant best practice. The plant equipment shall thereafter be implemented in full accordance with the details and mitigation provided in the approved Noise Impact Assessment before it is first brought into use and shall be maintained as such in perpetuity thereafter.

 

Reason: In the interest of the residential amenity of future occupiers in accordance with the National Planning Policy Framework (2021), Policies KP2 and CP4 of the Core Strategy (2007), Policies DM1 and DM3 of the Development Management Document (2015).

 

7 Hours of works associated with this permission shall only be 8am - 6pm Monday to Friday, 8am - 1pm Saturday. No works shall be carried out on Sundays or Bank or Public Holidays.

 

Reason: In the interests of the residential amenity of the adjoining residents and to ensure that the development complies with the National Planning Policy Framework (2021), Core Strategy (2007) Policies KP2 and CP4, Development Management Document (2015) policies DM1 and DM3 and the Southend Design and Townscape Guide (2009).

 

8 The windows proposed within the development hereby approved shall only be glazed in obscure glass (the glass to be obscure to at least Level 4 on the Pilkington Levels of Privacy, or such equivalent as may be agreed in writing with the local planning authority) and fixed shut, except for any top hung fan light which shall be a minimum of 1.7 metres above the internal finished floor level of the room or area served before the development is occupied and shall be retained as such in perpetuity thereafter. In the case of multiple or double-glazed units at least one layer of glass in the relevant units shall be glazed in obscure glass to at least Level 4.

 

Reason: In the interests of the residential amenity of the adjoining residents and to ensure that the development complies with the National Planning Policy Framework (2021), Core Strategy (2007) Policies KP2 and CP4, Development Management Document (2015) policies DM1 and DM3 and The Southend-on-Sea Design and Townscape Guide (2009)

 

9 Waste produced in association with the commercial operation of 54 The Ridgeway shall only be stored on the land known as '54 The Ridgeway' edged red on the approved location plan [Drawing No. 16A] and at no other location.

 

Reason: To ensure that the development is satisfactorily serviced and that satisfactory waste management is undertaken in the interests of highway safety and visual amenity and to protect the character of the surrounding area, in accordance with Policies KP2, CP3 and CP4 of the Core Strategy (2007) and Policies DM1 and DM15 of the Development Management Document (2015)

 

Informative

 

1 You are advised that as the proposed extension(s) or change of use to your property equates to less than 100sqm of new floorspace and does not involve the creation of a new dwelling (Class C3), the development benefits from a Minor Development Exemption under the Community Infrastructure Levy Regulations 2010 (as amended) and as such no charge is payable. See www.southend.gov.uk/cil for further details about CIL.

 

2 You should be aware that in cases where damage occurs during construction works to the highway in implementing this permission that Council may seek to recover the cost of repairing public highways and footpaths from any party responsible for damaging them. This includes damage carried out when implementing a planning permission or other works to buildings or land. Please take care when carrying out works on or near the public highways and footpaths in the borough.

 

Positive and Proactive Statement

 

The Local Planning Authority has acted positively and proactively in determining this application by assessing the proposal against all material considerations, including planning policies and any representations that may have been received and subsequently determining to grant planning permission in accordance with the presumption in favour of sustainable development, as set out within the National Planning Policy Framework. The detailed analysis is set out in a report on the application prepared by officers.

 

Supporting documents:

 

Get the best from this site

We use simple text files called 'cookies'. Some of these cookies are essential to make our site work and others help us to improve by giving us some insight into how the site is being used. For more information, including how to turn cookies off, see more about cookies - or simply click the Continue button to use this site as normal.