Agenda item
Draft Capital Programme 2017/18 to 2020/21
- Meeting of Cabinet, Thursday, 19th January, 2017 2.00 pm (Item 648.)
- View the background to item 648.
Report of the Corporate Management Team
Minutes:
The Cabinet considered a report of the Corporate Management Team setting out a draft programme of capital projects for the period 2017/18 to 2020/21.
It was noted that the Council had been notified of a successful bid to the Department for Education for a grant of £536k for the expansion of early years (3-4 year olds) places in preparation for the 30 hour entitlement for working parents in September 2017. The grant will be included in the final capital report to Cabinet on 14th February 2017.
Resolved:-
1. That the current approved Programme for 2017/18 to 2019/20 of £125.4m, as set out in Appendix 1 to the submitted report, be noted.
2. That the changes to the approved Programme, as set out in Appendix 2 to the report, be noted.
3. That the proposed new schemes and additions to the Capital Programme for the period 2017/18 to 2020/21 totalling £59.1m of which £52.9m is for the General Fund and £6.2m for the Housing Revenue Account, as set out in Appendices 6 and 7 to the report, be endorsed.
4. That the proposed schemes subject to external funding approval for the period 2017/18 to 2020/21 totalling £42.6m as set out in Appendices 2 and 7 to the report, be endorsed.
5. That it be noted that the proposed new schemes and additions, as set out in Appendices 6 and 7 to the report, and other adjustments as set out in Appendix 2 to the report, will result in a proposed capital programme (excluding schemes subject to external funding approval) of £185.8m for 2017/18 to 2020/21.
6. That it be noted that of the total programme of £185.8m for the period 2017/18 to 2020/21, the level of external funding supporting this programme is £58.2m.
7. That it be noted that a final review is being undertaken on the 2016/17 outturn and that the results will be included in the report to Cabinet on 14th February 2017.
Reason for Decision
The proposed Capital Programme is compiled from a number of individual projects which either contribute to the delivery of the Council’s objectives and priorities or enhance the Council’s infrastructure.
Other Options
The proposed Capital Programme is compiled from a number of individual projects, any of which can be agreed or rejected independently of the other projects
Note:- This is
an Executive Function save that approval of the final budget
following Cabinet on 14th February 2017 is a Council
Function.
Referred direct to all three Scrutiny
Committees.
Executive Councillor:- Lamb
Supporting documents:
- CE19-Cabinet report - Draft Capital Programme - 17-18 to 20-21 - 19 January 2017, item 648. PDF 125 KB
- CE19-Appendix 1 - Approved Capital Programme - November 16, item 648. PDF 143 KB
- CE19-Appendix 2 - Changes to Approved Capital Programme, item 648. PDF 14 KB
- CE19-Appendix 3 - Virements Between Approved Schemes, item 648. PDF 12 KB
- CE19-Appendix 4 - Re-profiles Between Years, item 648. PDF 18 KB
- CE19-Appendix 5 - New External Funding, item 648. PDF 12 KB
- CE19-Appendix 5a - LTP3 - Capital Actions and Allocations, item 648. PDF 191 KB
- CE19-Appendix 6 - Proposed New Schemes and Additions to the Capital Programme, item 648. PDF 28 KB
- CE19-Appendix 7 - Proposed New Schemes and Additions - descriptions, item 648. PDF 163 KB
- CE19-Appendix 8 - Amended Capital Programme 2017-18 to 2020-21, item 648. PDF 157 KB