Draft Capital Programme 2018/19 to 2021/22

The report has been circulated with the Cabinet Agenda for its meeting on 18th January 2018. The relevant Minute and report has been referred direct to all Scrutiny Committees for consideration.

Minutes:

The Committee considered Minute 647 of Cabinet held on 18th January 2018, which had been referred direct by Cabinet to all three Scrutiny Committees together with a report of the Corporate Management Team setting out the draft programme of capital projects for the period 2018/19 to 2021/22.

 

Resolved:-

 

That the following decisions of Cabinet be noted:-

 

“1. That the current approved Programme for 2018/19 to 2020/21 of £166.5m, as set out in Appendix 1 to the submitted report, be noted.

 

2.  That the changes to the approved Programme, as set out in Appendix 2 to the submitted report, be noted.

 

3.  That the proposed new schemes and additions to the Capital Programme for the period 2018/19 to 2021/22 totalling £20.1m for the General Fund as set out in Appendices 6 and 7 to the submitted report, be endorsed.

 

4.  That the proposed scheme subject to external funding approval for the period 2018/19 to 2021/22 totalling £19m as set out in Appendices 2 and 7 to the submitted report, be endorsed.

 

5.  That it be noted that the proposed new schemes and additions, as set out in Appendices 6 and 7 to the submitted report, and other adjustments as set out in Appendix 2 to the report, will result in a proposed capital programme (excluding schemes subject to external funding approval) of £184.9m for 2018/19 to 2021/22.

 

6.  That it be noted that of the total programme of £184.9m for the period 2018/19 to 2021/22, the level of external funding supporting this programme is £71.7.2m as set out in paragraph 7.1 of the submitted report.

 

7.  That it be noted that a final review is being undertaken on the 2017/18 projected outturn and that the results will be included in the report to Cabinet on 13th February 2018.”

 

Note:- This is an Executive Function save that approval of the final budget following Cabinet on 13th February 2018 is a Council Function.
Executive Councillor:- Lamb

Supporting documents:

 

Get the best from this site

We use simple text files called 'cookies'. Some of these cookies are essential to make our site work and others help us to improve by giving us some insight into how the site is being used. For more information, including how to turn cookies off, see more about cookies - or simply click the Continue button to use this site as normal.