Agenda item

18/00810/FULM - 10 Fairfax Drive, Westcliff-on-Sea (Prittlewell Ward)

Minutes:

Proposal: Demolish existing buildings, erect three blocks of three, four and five storeys comprising of 92 self-contained flats with balconies and parking at ground floor level, landscaping, amenity space, associated works including highway alterations and alteration of existing access onto Fairfax Drive (Amended Proposal)

Applicant: Weston Homes PLC

Agent: N/A

 

Resolved: (a) That the Deputy Chief Executive (Place), Director of Planning and Transport or the Group Manager Planning and Building Control be DELEGATED to GRANT PLANNING PERMISSION subject to completion of a legal agreement under S106 of the Town and Country Planning Act 1990 (as amended).

 

·         9 units of affordable housing (7 x 1 bed, 2 x 2 bed) all of which constitute shared ownership and an affordable housing review mechanism.

·         £45,400.50 contribution towards secondary education.

·         £4000 payable to the Council for expenditure towards covering the cost of the alterations of the Traffic Regulations Order in force along Fairfax Drive.

·         Travel packs

·         £4,600 towards biodiversity mitigation, management, protection and education.

 

(b) The Deputy Chief Executive (Place), Director of Planning and Transport or the Group Manager (Planning & Building Control) be authorised to determine the application upon completion of the above obligation, so long as planning permission when granted and the obligation when executed, accords with the details set out in the report submitted and the conditions listed below;

 

01 - The development hereby permitted shall be begun not later than 3 years beginning with the date of this permission.

 

Reason: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990

 

02 - The development shall be carried solely out in accordance with the approved plans:   WH181/17/P/35.01, WH1XX/17/P/05.01, AP234-P008 Rev E, AP234-P009 Rev E, AP234-P010 Rev E, WH181/18/P/05.02, AP234-P002 Rev E, AP234-P003 Rev E, AP234-P004 Rev F, AP234-P005 Rev E, AP234-P006 Rev E, AP234-P007 Rev E, AP234_201, PL1610.1.GA.300 01, PL1610.1.G1.301 01, PL1610.1.GA.302 01, PL1610.1.GA.200 01, PL1610.1.GA.201 01, PL1610.1.GA.101 02, PL1610.1.GA.102 02, PL1610.1.GA.100 02, PL1610.1.GA.202 01, PL1610.1 Planting schedule, 170429-TK07 Rev. A, 170429-05 Rev. C

 

Reason: To ensure the development is carried out in accordance with the development plan.

 

03 - Notwithstanding the details shown on the plans submitted and otherwise hereby approved, no construction works above the lower ground floor slab level shall take place until samples of the materials to be used in the construction of the external elevations of the building hereby permitted, including roofs, cladding, balconies, balustrades, screening and fenestration, have been submitted to and approved in writing by the local planning authority. The development shall be finished in the approved facing brickwork Ibstock Leicester Multi and Ibstock Leicester Multi Yellow stock or any other brick details subsequently submitted to and approved in writing by the local planning authority. The development shall be carried out only in full accordance with the approved details.

 

Reason: To safeguard character and appearance of the area and amenities of neighbouring occupiers in accordance with Policies KP2 and CP4 of the Core Strategy (2007), Policies DM1 and DM3 of the Development Management Document (2015) and the Design and Townscape Guide (2009).

 

04 - The development shall be undertaken in strict accordance with the approved hard and soft landscaping plans and particulars or any other hard and soft landscaping details that have been previously submitted to and approved in writing by the local planning authority. The hard landscaping shall be completed prior to first occupation of the development and soft landscaping/planting shall be completed within the planting season following first occupation of the development (or within any other time limit agreed in writing with the local planning authority). If any trees are removed or found to be dying, severely damaged or diseased within 5 years of planting them, they must be replaced with trees of a similar size and species as may be agreed with the Local Planning Authority.

 

Reason: To safeguard character and appearance of surrounding area in accordance with Policies KP2 and CP4 of the Core Strategy (2007), Policies DM1 and DM3 of the Development Management Document (2015) and the Design and Townscape Guide (2009).

 

05 - The development hereby approved shall be carried out and completed in accordance with drawing AP234-P0002 Revision E dated 09/03/18 in relation to the highways works and new access road shown for the development in accordance with a timescale that has been submitted to the local planning authority and approved in writing before the development is first occupied.

 

Reason: In the interests of highways management and safety in accordance with Core Strategy (2007) policies KP2, CP3, CP4; Development Management Document (2015) policy DM15 and the advice contained within the Design and Townscape Guide (2009).

 

06 - The development shall not be occupied until 92 car parking spaces, of which 10 shall be for disabled users, have been provided at the site and made available for use in accordance with drawing AP234-P002 Revision E (dated 09/03/18) together with properly constructed vehicular accesses to the adjoining highway, all in accordance with the approved plans.  The parking spaces shall be permanently retained thereafter for the parking of occupiers of and visitors to the development.

 

Reason: To ensure that adequate car parking is provided and retained to serve the development in accordance with Policy CP3 of the Core Strategy (2007) and Policy DM15 of the Council’s Development Management Document (2015).

 

07 - The development shall not be occupied until details of all balcony and terrace areas within the development and how they will be served by privacy screens have been submitted to and approved in writing by the Local Planning Authority.  The screens, as approved, shall be erected prior to first occupation of those balconies/ terrace areas, and retained thereafter in perpetuity. No flat roof areas within the development shall be used for the purposes of a sitting out, balcony or amenity area unless it has been specifically approved as part of the above details.

 

Reason: In the interest of the visual amenities and character of the area, and to protect the amenities of surrounding occupiers in accordance with Policies  KP2 and CP4 of the Core Strategy (2007) and Policy DM1 of the Development Management Document (2015).

 

08 - The development shall not be occupied until the secure, covered cycle parking spaces to serve the development as shown on drawing AP234-P0002 Rev. E (dated 09/03/18) have been provided at the site and made available for use in full accordance with the approved plans. The approved scheme shall be permanently maintained thereafter.

 

Reason: To ensure that adequate cycle parking is provided and retained to serve the development in accordance with Policies CP3 of the Core Strategy (2007) and Policy DM15 of the Development Management Document (2015).

 

09 - The development shall be undertaken in accordance with the approved Construction Phase (Health, Safety and Environment) Plan (Construction Method Statement) by SES reference WH181 dated March 2018 – version 1 or any other construction method statement previously submitted to and approved in writing for this development by the local planning authority.

 

Reason: In the interests of visual amenity and the amenities of neighbouring occupiers and to ensure a satisfactory standard of landscaping pursuant to Policy CP4 of the Core Strategy (2007) and Policy DM1 of the Development Management Document (2015).

 

10 - No surface water drainage works shall take place until details of the implementation, maintenance and management of a scheme for surface water drainage works incorporating Sustainable Urban Drainage (SUDS) Principles have been submitted to and approved by the local planning authority. The scheme shall be implemented in accordance with the approved details before the development is occupied and brought into use and be managed and maintained as such thereafter. Those details shall include:

 

i)   An investigation of the feasibility of infiltration SUDS as the preferred approach to establish if the principles of any infiltration based surface water drainage strategy are achievable across the site, based on ground conditions. Infiltration features should be included where infiltration rates allow; 

 

ii)  Drainage plans and drawings showing the proposed locations and dimensions of all aspects of the proposed surface water management scheme.  The submitted plans should demonstrate the proposed drainage layout will perform as intended based on the topography of the site and the location of the proposed surface water management features; 

 

iii)   a timetable for its implementation; and

 

vii)  a management and maintenance plan for the lifetime of the development which shall include the arrangements for adoption by any public body or statutory undertaker, or any other arrangements to secure the operation of the sustainable drainage scheme throughout its lifetime.

 

Reason: To prevent flooding by ensuring the satisfactory storage and disposal of surface water from the site for the lifetime of the development and to prevent environmental and amenity problems arising from flooding in accordance with Policies KP2 and CP4 of the Core Strategy (2007) and Policy DM2 of the Development Management Document (2015).

 

11 - A scheme detailing how at least 10% of the total energy needs of the development will be supplied using on site renewable sources must be submitted to and agreed in writing prior to occupation of the development hereby approved by the Local Planning Authority and implemented in full prior to the first occupation of the development. This provision shall be made for the lifetime of the development.

 

Reason: In the interests of providing sustainable development in accordance with Policy KP2 of the Core Strategy (2007) and Development Management Document (2015) Policy DM2.

 

12 - Before the development is first occupied or brought into use, the dwellings in blocks C and D/E hereby approved shall be carried out in a manner to ensure that they comply fully with the building regulation M4 (2) standard.

 

Reason: To ensure the residential units hereby approved provides high quality and flexible internal layouts to meet the changing needs of residents in accordance with National Planning Policy Framework (2018), Core Strategy (2007) Policy KP2, Development Management Document (2015) Policy DM2 and the Design and Townscape Guide (2009).

 

13 - Prior to occupation of the development hereby approved details of the water efficient design measures set out in Policy DM2 (iv) of the Development Management Document to limit internal water consumption to 105 litres per person  per  day  (lpd)  (110  lpd  when  including  external  water  consumption), including measures of water efficient fittings, appliances and water recycling systems such as grey water and rainwater harvesting shall be submitted to and approved in writing by the local planning authority. The development shall be implemented in accordance with the approved details before it is occupied and shall be retained as such in perpetuity.

 

Reason: To minimise the environmental impact of the development through efficient use of water in accordance with the National Planning Policy Framework (2018) Core Strategy (2007) Policy KP2, Development Management Document (2015) Policy DM2 and the Design and Townscape Guide (2009).

 

14 - Notwithstanding the details shown in the plans submitted and otherwise hereby approved, the development hereby granted consent shall not be occupied or brought into use unless and until plans are submitted to the Local Planning Authority and approved in writing which clearly specify all the windows and other openings in the development that are to be permanently glazed with obscured glass and fixed shut or provided with only a fanlight (or other similar) opening and the manner and design in which these windows and openings are to be implemented. The development hereby permitted shall be implemented in full accordance with the details approved under this condition before it is first occupied or brought into use and shall be permanently retained as such thereafter. The windows included within such agreed scheme shall be glazed in obscure glass which is at least Level 4 on the Pilkington Levels of Privacy, or such equivalent as may be agreed in writing with the local planning authority. Top hung lights agreed within such scheme shall be a minimum of 1.7 metres above internal floor level. In the case of multiple or double glazed units at least one layer of glass in the relevant units shall be glazed in obscure glass to at least Level 4. The windows shall be retained in accordance with the agreed details in perpetuity thereafter.

 

Reason: To avoid overlooking and the resultant loss of privacy of the adjoining residential properties, in accordance with the National Planning Policy Framework (2018), Core Strategy (2007) Policies KP2 and CP4, and Development Management Document (2015) Policy DM1 and advice contained within the Design and Townscape Guide (2009).

 

15 - No development above the current ground level shall take place until a detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property and the natural environment from contaminated land have been submitted to and approved in writing by the Local Planning Authority. The remediation scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, an appraisal of remedial options, and proposal of the preferred option(s), and a timetable of works and site management procedures. The approved remediation scheme shall be implemented in full prior to the first occupation of the dwellings hereby approved. The scheme must ensure that the site will not qualify as contaminated land under Part IIA of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation.

 

Reason: To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other off-site receptors in accordance with Core Strategy (2007) policy KP2 and Policies DM1 and DM14 of the Development Management Document (2015).

 

16 - All the noise mitigation measures outlined in the Environmental Noise Assessment Report No. ENV1-SOUT-040 version 2 of 29 November 2017 to protect future residents of the building from the impact of vehicular noise along Fairfax Drive and noise from football stadium activity must be implemented in their entirety prior to occupation of the buildings hereby approved to achieve an internal noise level of no greater than 30dB and the approved measures implemented shall be maintained in perpetuity.

 

Reason: In order to protect the amenities of occupiers of the development surrounding occupiers and to protect the character the area in accordance with policies KP2 and CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015).

 

17 - Notwithstanding the information submitted with the application and otherwise hereby approved, the development shall not be first occupied unless and until a car park management and waste strategy to include details of how parking on the site during match days at the adjoining Southend United Football Stadium and to include details of where visitors to the development will park has been submitted to and agreed in writing by the local planning authority. The development shall be implemented and completed in full accordance with the details approved under this condition before it is first occupied or brought into first use and the approved strategy shall be adhered to in full in perpetuity thereafter.

 

Reason:  To ensure that the development is satisfactorily serviced and that satisfactory waste management is undertaken in the interests of highway safety and visual amenity and to protect the character of the surrounding area, in accordance with Policies KP2 and CP3 of the Core Strategy (2007) and  Policy DM15 of the Development Management Document (2015).

 

18 - With reference to British Standard 4142, the noise rating level arising from all plant and extraction/ventilation equipment installed at this site in accordance with this consent shall be at least 5dB(A) below the prevailing background noise level at 3.5 metres from ground floor façades and 1 metre from all other façades of the nearest noise sensitive property with no tonal or impulsive character.

 

Reason: In order to protect the amenities of occupiers of the development surrounding occupiers and to protect the character and visual amenities of the area in accordance with Policies KP2 and CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015).

 

19 - Notwithstanding the details shown in the drawings submitted and otherwise hereby approved the development shall not be implemented above the current ground level unless and until details of the levels of the proposed building, footpaths and other landscaped areas relative to adjoining land and any other changes proposed in the levels of the site associated with the works permitted by this permission have been submitted to and approved in writing by the Local Planning Authority. The development shall be implemented in full accordance with the details approved under this condition before it is first occupied or brought into use.

 

Reason: To ensure that the development is carried out at suitable levels in relation to adjoining land and the highway having regard to drainage and the amenities of the area and neighbouring occupiers.

 

20 - Before the development hereby approved is occupied bird and bat boxes shall be installed at the site in accordance with the recommendations on Page 16 of the Phase 1 Habitats Survey (extended) by Wildlife Matters dated 15 June 2017 submitted with this application. The installed boxes shall be permanently maintained thereafter.

 

Reason: To ensure that the development contributes to local ecology in accordance with the National Planning Policy Framework (2018) and Policies KP2 and CP4 of the Council’s Core Strategy (2007).

 

21 - Before the development is occupied or brought into use, and notwithstanding details shown on the plans hereby approved, units B12, B13 and B14 on the ground floor of Block B shall be implemented as wheelchair accessible units to ensure compliance with the building regulation M4(3) standard in accordance with details which shall previously have been submitted to and approved in writing by the Local Planning Authority.

 

Reason: To ensure the development includes units suitably accessible for people using wheelchairs in accordance with the National Planning Policy Framework (2018), the Core Strategy (2007) Policy KP2, Policy DM8 of the Development Management Document (2015) and the Council’s Design and Townscape Guide (2009).

 

22 - The development shall not be occupied until a scheme of highway signage both for the internal roadway within the site and outside the site in the vicinity of the site access/ egress, such scheme to incorporate signage to inform drivers about prohibited right turn movements into and from Fairfax Drive, has been submitted to and approved in writing by the Local Planning Authority. These works shall also form part of a Section 278 Highways Agreement. All the approved signage shall be implemented in full accordance with those approved details, prior to occupation of any of the development and shall be permanently maintained thereafter.

 

Reason: To ensure that traffic movement is satisfactorily managed in the interests of highway traffic management and highway safety in accordance with Policies KP2 and CP3 of the Core Strategy (2007) and Policy DM15 of the Development Management Document (2015).

 

(c) In the event that the planning obligation referred to in part (a) above has not been completed by  27th February 2019 (or an extension of this time as may be agreed by the Director of Planning and Transport or Group Manager Planning & Building Control), the Deputy Chief Executive (Place), Director of Planning and Transport or Group Manager of Planning and Building Control be authorised to refuse planning permission for the application on the grounds that the development would not provide for affordable housing, highway works, travel packs, biodiversity mitigation or education provision and that as such the proposal would be unacceptable and contrary to Policies KP2, KP3, CP3, CP6 and CP8 of the Core Strategy (2007) and Policies DM1, DM3, DM7 and DM15 of the Development Management Document (2015).

 

The Local Planning Authority has acted positively and proactively in determining this application by identifying matters of concern with the proposal and determining the application within a timely manner, clearly setting out the reason(s) for refusal, allowing the Applicant the opportunity to consider the harm caused and whether or not it can be remedied by a revision to the proposal.  The detailed analysis is set out in a report prepared by officers. In the circumstances the proposal is not considered to be sustainable development. The Local Planning Authority is willing to discuss the best course of action.

 

Informatives

 

01 - Please note that the development the subject of this application is liable for a charge under the Community Infrastructure Levy Regulations 2010 (as amended). A Community Infrastructure Levy (CIL) Liability Notice will be issued as soon as practicable following this decision notice. This contains details including the chargeable amount, when this is payable and when and how exemption or relief on the charge can be sought. You are advised that a CIL Commencement Notice (CIL Form 6) must be received by the Council at least one day before commencement of development. Receipt of this notice will be acknowledged by the Council. Please ensure that you have received both a CIL Liability Notice and acknowledgement of your CIL Commencement Notice before development is commenced. Most claims for CIL relief or exemption must be sought from and approved by the Council prior to commencement of the development.

 

Charges and surcharges may apply, and exemption or relief could be withdrawn if you fail to meet statutory requirements relating to CIL. Further details on CIL matters can be found on the Council's website at www.southend.gov.uk/cil.

 

02 - The applicant is reminded that this permission does not bestow compliance with other regulatory frameworks. In particular your attention is drawn to the statutory nuisance provisions within the Environmental Protection Act 1990 (as amended) and also to the relevant sections of the Control of Pollution Act 1974. The provisions apply to the construction phase and not solely to the operation of the completed development. Contact 01702 215005 for more information.

 

03 - You are advised that a Highways Licence/Agreement needs to be in place before any works are carried out to the public highway and any works to public transport infrastructure (e.g. bus stops) will need to be carried out by a Council approved contractor.

 

04 - This permission is governed by a legal agreement between the applicant and the Borough Council under Section 106 of the Town and Country Planning Act 1990. The agreement relates to a financial contribution towards affordable housing, secondary education and biodiversity mitigation, management protection and education.

 

05 - The works to existing highway will require a Section 278 agreement or Highways Licence.

 

Supporting documents:

 

Get the best from this site

We use simple text files called 'cookies'. Some of these cookies are essential to make our site work and others help us to improve by giving us some insight into how the site is being used. For more information, including how to turn cookies off, see more about cookies - or simply click the Continue button to use this site as normal.