Proposal:  Erect four two storey dwellinghouses with associated parking and amenity space

Applicant:  The Garrison LLP

Agent:  APS Design Associates Ltd.

 

Planning Permission GRANTED subject to the following conditions:

 

01  The development hereby permitted shall be begun not later than 3 years beginning with the date of this permission.

 

Reason: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990

 

02  The development shall be carried out in accordance with the approved plans: 01; 04; 05; 06; 07.

 

Reason: Reason: To ensure the development is carried out in accordance with the development plan.

 

03  The development hereby approved shall be carried out in accordance with the Flood Risk Assessment prepared by Evolve dated August 2015.

 

Reason: To ensure the site is protected to the standard that the development is designed and modelled to within the submitted Flood Risk Assessment NPPF and policy KP2 of Core Strategy.

 

04  The development hereby permitted shall operate at all time in accordance with the 'Flood Evacuation and Warning Plan' received 22.09.2016 reference CC/1687.

 

Reason: To ensure that the Flood Warning and Evacuation Plan meets with the requirements of the Environment Agency's Flood Warning Service.

 

05  No development shall take place until full details of both hard and soft landscape works, have been submitted to and approved in writing by the local planning authority and the approved hard landscaping works shall be carried out prior to first occupation of the development and the soft landscaping works within the first planting season following first occupation of the development, unless otherwise agreed in writing by the local planning authority. These details shall include, for example:-

i  proposed finished levels or contours; 

ii.  means of enclosure, including any gates to the car parks; 

iii.  car parking layouts; 

iv.  other vehicle and pedestrian access and circulation areas; 

v.  hard surfacing materials; 

vi. minor artefacts and structures (e.g. street furniture, loggia, bollards, play equipment, refuse or other storage units, signs, lighting, etc.) 

This shall include details of details of the number, size and location of the trees, shrubs and plants to be planted together with a planting specification, details of the management of the site, e.g. the uncompacting of the site prior to planting, the staking of trees and removal of the stakes once the trees are established, details of measures to enhance biodiversity within the site and tree protection measures to be employed during demolition and construction.

 

Reason: In the interests of visual amenity and the amenities of occupiers and to ensure a satisfactory standard of landscaping pursuant to Policy DM1 of the Development Management DPD and Policy CP4 of the Core Strategy DPD1

 

06  A scheme detailing how at least 10% of the total energy needs of the dwellinghouses will be supplied using on site renewable sources must be submitted to and agreed in writing by the Local Planning Authority and implemented in full prior to the first occupation of the dwellinghouse. This provision shall be made for the lifetime of the development.

 

Reason: In the interests of providing sustainable development in accordance with Policy KP2 of the Core Strategy and policy DM2 of the Development Management Document (DPD1).

 

07  Prior to occupation of the development hereby approved details of the water efficient design measures set out in Policy DM2 (iv) of the Development Management Document to limit internal water consumption to 105 litres per person  per  day  (lpd)  (110  lpd  when  including  external  water  consumption), including measures of water efficient fittings, appliances and water recycling systems such as grey water and rainwater harvesting.

 

Reason: To minimise the environmental impact of the development through efficient use of water in accordance with the National Planning Policy Framework, DPD1 (Core Strategy) policy KP2, DPD2 (Development Management Document) policy DM2 and SPD1 (Design and Townscape Guide).

 

08  The development hereby approved shall be carried out in accordance with drawing to ensure the dwellinghouses comply with building regulation M4 (2)-‘accessible and adaptable dwellings’.

 

Reason: To ensure the residential units hereby approved provides high quality and flexible internal layouts to meet the changing needs of residents in accordance with National Planning Policy Framework, DPD1 (Core Strategy) policy KP2, DPD2 (Development Management Document) policy DM2 and SPD1 (Design and Townscape Guide).

 

09  Details of an acoustic fence, to be erected along the northern boundary of the site, shall be submitted to and agreed in writing by the Local Planning Authority and the development shall be carried only in accordance with the agreed details, unless otherwise agreed in writing by the Local Planning Authority.

 

Reason: To safeguard the amenities of future occupiers in accordance with policy DM1 of the Development Management Document DPD2.

 

10   (a) No development shall take place until a written scheme of investigation for a programme of archaeological work has been submitted to and approved in writing by the local planning authority. This must include details of the suitably qualified person or organisation that will carry out the archaeological work.

(b) The archaeological work and development must then be carried out in accordance with the approved scheme.  A written report of the investigation and findings must be produced, showing that the archaeological work and development has been carried out in accordance with the approved scheme.  Copies of the written report of the investigation and findings must be sent to Southend Borough Council,

(c)  No part of the new building can be used until the local planning authority has provided written confirmation that the archaeological fieldwork and development has been carried out in accordance with the approved scheme.

 

Reason:  To avoid damage to archaeological remains on site as set out in DPD1 (Core Strategy) policy KP2 and CP4, DPD2 (Development Management Document) Policy DM5  and SPD1 (Design and Townscape Guide).

 

Informative

 

01  Please note that the development the subject of this application is liable for a charge under the Community Infrastructure Levy Regulations 2010 (as amended). Enclosed with this decision notice is a Community Infrastructure Levy (CIL) Liability Notice for the attention of the applicant and any person who has an interest in the land. This contains details including the chargeable amount, when this is payable and when and how exemption or relief on the charge can be sought. You are advised that a CIL Commencement Notice (CIL Form 6) must be received by the Council at least one day before commencement of development. Receipt of this notice will be acknowledged by the Council. Please ensure that you have received both a CIL Liability notice and acknowledgement of your CIL Commencement Notice before development is commenced. Most claims for CIL relief or exemption must be sought from and approved by the Council prior to commencement of the development. Charges and surcharges may apply, and exemption or relief could be withdrawn if you fail to meet statutory requirements relating to CIL. Further details on CIL matters can be found on the Council's website at www.southend.gov.uk/cil.

 

The Local Planning Authority has acted positively and proactively in determining this application by identifying matters of concern with the proposal and determining the application within a timely manner, clearly setting out the reason(s) for refusal, allowing the Applicant the opportunity to consider the harm caused and whether or not it can be remedied by a revision to the proposal.  The detailed analysis is set out in a report prepared by officers. In the circumstances the proposal is not considered to be sustainable development. The Local Planning Authority is willing to discuss the best course of action and is also willing to provide pre-application advice in respect of any future application for a revised development, should the applicant wish to exercise this option in accordance with the Council's pre-application advice service.

Supporting documents:

 

Get the best from this site

We use simple text files called 'cookies'. Some of these cookies are essential to make our site work and others help us to improve by giving us some insight into how the site is being used. For more information, including how to turn cookies off, see more about cookies - or simply click the Continue button to use this site as normal.