Agenda item

16/01780/FULM - 1307 London Road, Leigh-on-Sea, Essex, SS9 2AD (Belfairs Ward)

Minutes:

Proposal:  Demolish existing building and erect three storey building comprising of 16 self-contained flats on first and second floor with balconies and roof terrace with retail unit on ground floor, lay out parking bin store and alter vehicular access at 1307-1313 London Road

Applicants:  Dove Jeffry Homes

 

Resolved: (a) That the Deputy Chief Executive (Place), Director for Planning & Transport or the Group Manager Planning & Building Control be DELEGATED to GRANT planning permission subject to the completion of a PLANNING AGREEMENT UNDER SECTION 106 of the Town and Country Planning Act 1990 (as amended) and all appropriate legislation to seek the provision of:

 

(a)  2 x 1 bedroom affordable units (Affordable Rented); and

(b)  1 x 2 bedroom affordable units (Shared Ownership)

 

(b) That the Deputy Chief Executive (Place), Director for Planning & Transport or the Group Manager Planning & Building Control be authorised to determine the application upon completion of the above obligation, so long as planning permission when granted and the obligation when executed, accords with the details set out in the report submitted and the conditions listed below:

 

01  The development hereby permitted shall be begun not later than 3 years beginning with the date of this permission.

 

Reason: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990

 

02  The development shall be carried out in accordance with the approved plans:  001 P1, 200 P5, 201 P1, 202 P2 and 203 P1.

 

Reason: To ensure the development is carried out in accordance with the development plan.

 

03  Notwithstanding the details shown on the plans submitted and otherwise hereby approved, no construction works above the floor slab level shall take place until samples of the materials to be used in the construction of the external elevations of the building hereby permitted, including balconies, balustrades, screening, fenestration, front porches and hoods have been submitted to and approved in writing by the local planning authority. Development shall be carried out in accordance with the approved details.

 

Reason: To safeguard character and appearance of surrounding area in accordance with Policies KP2 and CP4 of the BLP and Policy DM1 of the Development Management DPD 2015

 

04  No construction works above the floor slab level shall take place until full details of both hard and soft landscape works have been submitted to and approved in writing by the local planning authority.  These details shall include: proposed finished levels or contours; means of enclosure (including any gates to the car parks); car parking layouts;  other vehicle and pedestrian access and circulation areas;  hard surfacing materials;  minor artefacts and structures (e.g. furniture, loggia, bollards, play equipment, refuse or other storage units, signs, lighting etc.)  Details for the soft landscape works shall include the number, size and location of the trees, shrubs and plants to be planted together with a planting specification, the management of the site (e.g. the uncompacting of the site prior to planting) and the initial tree planting and tree staking details.  The development shall be implemented in full accordance with the approved details before it is occupied or brought into use.

 

Reason: In the interests of visual amenity and the amenities of occupiers and to ensure a satisfactory standard of landscaping pursuant to Policy CP4 of the Core Strategy DPD1 with CP4 of the Core Strategy DPD1 and Policy DM1 of the Development Management DPD 2015.

 

05  The development shall not be occupied until space has been laid out within the site in accordance with drawing No. 201 P1 for cars to be parked and for the loading and unloading of vehicles and for vehicles to turn so that they may enter and leave the site in a forward gear.  The parking spaces shall be permanently retained thereafter for the parking of occupiers, staff and visitors to the development. 

 

Reason: To ensure that adequate car parking is provided and retained to serve the development in accordance with Policies CP3 of the Core Strategy DPD1 and Policy DM15 of the Development Management DPD 2015.

 

06  The development shall not be occupied until a waste management plan and service plan has been submitted to and agreed in writing by the Local Planning Authority.  The waste management and servicing of the development shall thereafter be carried out in accordance with the approved details. 

 

Reason:  to ensure that the development is satisfactorily serviced and that satisfactory waste management is undertaken in the interests of highway safety and visual amenity and to protect the character of the surrounding area, in accordance with Policies KP2 and CP3 of the Core Strategy DPD1 and  Policy DM15 of the Development Management DPD 2015.

 

07  The development shall not be occupied until details of the secure, covered cycle parking spaces to serve the residential development and cycle parking spaces to serve the retail/commercial unit have been submitted to and agreed in writing by the Local Planning Authority. The approved scheme shall be implemented prior to first occupation and shall be retained thereafter. 

 

Reason: To ensure that adequate cycle parking is provided and retained to serve the development in accordance with Policies CP3 of the Core Strategy DPD1 and Policy DM15 of the Development Management DPD 2015.

 

08  No development shall take place, including any works of demolition, until a Construction Method Statement has been submitted to, and approved in writing by, the local planning authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide, amongst other things, for:

 

(i)  the parking of vehicles of site operatives and visitors

(ii)  loading and unloading of plant and materials

(iii)  storage of plant and materials used in constructing the development

(iv)  the erection and maintenance of security hoarding 

(v)  measures to control the emission of dust and dirt during construction

(vi)  a scheme for recycling/disposing of waste resulting from demolition and construction works that does not allow for the burning of waste on site.

 

Reason: In the interests of visual amenity and the amenities of occupiers and to ensure a satisfactory standard of landscaping pursuant to Policy CP4 of the Core Strategy DPD1 with CP4 of the Core Strategy DPD1 and Policy DM1 of the Development Management DPD 2015.

 

09  Before the A2 use hereby permitted is occupied, details of any equipment to be installed to control the emission of fumes and smell from the premises shall be submitted to and approved in writing by the Local Planning Authority. The scheme as approved shall be implemented before the unit is brought into use. All equipment installed as part of the scheme shall thereafter be operated and maintained in accordance with the manufacturer's instructions.

 

Reason: In order to protect the amenities of occupiers of the development surrounding occupiers and to protect the character and visual amenities of the area in accordance with policies KP2 and CP4 of the Core Strategy DPD1 and Policies DM1 and DM3 of the Development Management DPD 2015.

 

10  With reference to BS4142, the noise rating level arising from all plant and extraction/ventilation equipment installed at the site shall be at least 5dB(A) below the prevailing background at 3.5 metres from ground floor façades of the nearest noise sensitive property and 1 metre from all other façades of the nearest noise sensitive property with no tonal or impulsive character. 

 

Reason: In order to protect the amenities of occupiers of the development surrounding occupiers and to protect the character and visual amenities of the area in accordance with policies KP2 and CP4 of the Core Strategy DPD1 and Policies DM1 and DM3 of the Development Management DPD 2015.

 

11  The Use Class A2 use hereby permitted shall not be open to customers outside the following times: 07:00 to 23:00 hours.

 

Reason: In order to protect the amenities of occupiers of the development surrounding occupiers and to protect the character and amenities of the area in accordance with policies KP2 and CP4 of the Core Strategy DPD1 and Policies DM1 and DM3 of the Development Management DPD 2015.

 

12  No deliveries or refuse collection shall be taken at or despatched from the Use Class A2 unit outside the hours of 07:00-19:00hours Mondays to Fridays and 08:00-13:00hours on Saturdays nor at any time on Sundays, Bank or Public Holidays.

 

Reason: In order to protect the amenities of occupiers of the development surrounding occupiers and to protect the character and amenities of the area in accordance with policies KP2 and CP4 of the Core Strategy DPD1 and Policies DM1 and DM3 of the Development Management DPD 2015.

 

13 Other than the demolition, grubbing up of foundations and site clearance, no development shall take place until a site investigation of the nature and extent of contamination has been carried out in accordance with a methodology which has previously been submitted to and approved in writing by the local planning authority. The results of the site investigation shall be made available to the local planning authority before any construction begins. If any contamination is found during the site investigation, a report specifying the measures to be taken to remediate the site to render it suitable for the development hereby permitted shall be submitted to and approved in writing by the local planning authority before any construction begins. The site shall be remediated in accordance with the approved remediation measures before development the development hereby approved is occupied and evidence to demonstrate that the remediation has taken place shall be submitted in writing to the Local Planning Authority before the development is occupied. 

 

If, during the course of development, any contamination is found which has not been identified in the site investigation, additional measures for the remediation of this source of contamination shall be submitted to and approved in writing by the local planning authority. The remediation of the site shall incorporate the approved additional measures and these shall be fully implemented before the site is occupied.

 

Reason: To ensure that any contamination on the site is identified and treated so that it does not harm anyone who uses the site in the future, and to ensure that the development does not cause pollution to Controlled Waters in accordance with DPD1 (Core Strategy) 2007 policy KP2 and Policies DM1 and DM14 of the Development Management DPD 2015. 

 

14  No construction works above the floor slab level shall take place until details of the implementation, maintenance and management of a scheme for surface water drainage works have been submitted to and approved by the local planning authority. The scheme shall be implemented and thereafter managed and maintained in accordance with the approved details before the development is occupied and brought into use. Those details shall include:

 

(i)  An investigation of the feasibility of infiltration SUDS as the preferred approach to establish if the principles of any infiltration based surface water drainage strategy are achievable across the site, based on ground conditions.  Infiltration or soakaway tests should be provided which fully adhere to BRE365 guidance to demonstrate this.  Infiltration features should be included where infiltration rates allow; 

 

(ii)  Drainage plans and drawings showing the proposed locations and dimensions of all aspects of the proposed surface water management scheme.  The submitted plans should demonstrate the proposed drainage layout will perform as intended based on the topography of the site and the location of the proposed surface water management features; 

 

(iii)   a timetable for its implementation; and

 

(vii)  a management and maintenance plan for the lifetime of the development which shall include the arrangements for adoption by any public body or statutory undertaker, or any other arrangements to secure the operation of the sustainable drainage scheme throughout its lifetime.

 

Reason: To prevent flooding by ensuring the satisfactory storage and disposal of surface water from the site for the lifetime of the development and to prevent environmental and amenity problems arising from flooding in accordance with Policy KP2 and CP4 of the Core Strategy 2007 and area in accordance with policies  KP2 and CP4 of the Core Strategy DPD1 and  Policy DM2 of the Development Management DPD 2015.

 

15  Details of any external lighting to be installed in the development shall be submitted to and approved in writing by the local planning authority before the development is occupied or brought into use.  Development shall be carried out in accordance with the approved details before the development is occupied or brought into use.  No additional external lighting shall be installed on the building without the consent of the Local Planning Authority. 

 

Reason: In the interest of the visual amenities and character of the area, and to protect the amenities of surrounding occupiers in accordance with policies  KP2 and CP4 of the Core Strategy DPD1 and with CP4 of the Core Strategy DPD1 and Policies DM1 of the Development Management DPD 2015.

 

16  The development shall be undertaken in accordance with the Energy and Sustainability Statement prepared by Fusion 13 that has been submitted with the application before the development is occupied or brought into use.  The PV panels shown on plan 201 P1 shall be fully installed prior to the first occupation of any of the flats hereby approved and all approved measures shall be retained for the lifetime of the development unless otherwise agreed in writing by the Local Planning Authority.

 

Reason: In the interests of providing sustainable development in accordance with Policy KP2 of the Core Strategy and Development Management Document policy DM2.

 

17  Demolition or construction works associated with this permission shall not take place outside 07:30hours to 18:00hours Mondays to Fridays and 08:00hours to 13:00hours on Saturdays nor at any time on Sundays or Bank Holidays.

 

Reason: In order to protect the amenities of occupiers of the development surrounding occupiers and to protect the character the area in accordance with policies KP2 and CP4 of the Core Strategy DPD1 and Policies DM1 and DM3 of the Development Management DPD 2015.

 

18 A landscape management plan, including long term design objectives, management responsibilities and maintenance schedules for all landscape areas, shall be submitted to and approved by the local planning authority prior to the occupation of the development.  The landscaping of the site shall be managed in accordance with the approved plan in perpetuity.

 

Reason: In the interests of visual amenity and the amenities of occupiers and to ensure a satisfactory standard of landscaping pursuant to Policy CP4 of the Core Strategy DPD1 and Policy DM1 of the Development Management DPD 2015.

 

19 The development shall be undertaken in full accordance with the recommendations set out at section 4.2 of the Noise Assessment prepared by Adrian James Acoustics Limited (Dated 23/03/16) that has been submitted with the application before the development is occupied or brought into use.

 

Reason: In order to protect the amenities of occupiers of the development in accordance with policies KP2 and CP4 of the Core Strategy DPD1 and Policies DM1 and DM3 of the Development Management DPD 2015.

 

20  Notwithstanding the details shown on the plans submitted and otherwise hereby approved, prior to the installation of any shopfront at the site, the details of the design, materials, glazing, doors, shutters, signage and lighting of the shopfront shall be submitted to and approved in writing by the Local Planning Authority.  The development shall be carried out in accordance with the approved details before the A2 use is brought into use and retained thereafter.  

 

Reason: In order to protect the character and visual amenities of the area in accordance with policies KP2 and CP4 of the Core Strategy DPD1 and Policy DM1 of the Development Management DPD 2015.

 

21  Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (as amended) (or any order revoking, re-enacting or modifying that Order), no structures such as canopies, fences, loggias, trellises or satellite or radio antennae shall be installed within the development or on the buildings unless otherwise previously agreed in writing by the Local Planning Authority. 

 

Reason: In order to protect the character and visual amenities of the development and surrounding area in accordance with policies KP2 and CP4 of the Core Strategy DPD1 and Policy DM1 of the Development Management DPD 2015.

 

22  The commercial floorspace hereby approved shall be used only for purposes falling within Use Class A2 and for no other purpose including any within Classes A1, A3, A4, A5, B1, C3 or D1 of the Town and Country Planning (Use Classes) Order 1987 as amended (or any statutory modification or re-enactment or replacement thereof (as the case may be) for the time being in force). 

 

Reason: In order to protect the amenities of occupiers of the development surrounding occupiers and to protect the character and amenities of the area in accordance with Policies KP2 and CP4 of the Core Strategy DPD1 and Policies DM1 and DM3 of the Development Management DPD 2015.

 

23  No demolition or other works associated with this permission shall take place until an Arboricultural Method Statement  &  Tree  Protection  Plan  has been submitted to and approved in writing by the Local Planning Authority.  Subsequently the development shall only be undertaken in full compliance with the approved details and the content of Section 6.0 (Recommendations) of the “Tree Survey, Arboricultural Impact Assessment, Preliminary Arboricultural Method Statement & Tree Protection Plan” dated 16/09/16 that has been submitted within this application.

 

Reason In the interests of amenity, to protect existing trees and to ensure a satisfactory standard of landscaping pursuant to Policy CP4 of the Core Strategy DPD1 Policy DM1 of the Development Management DPD 2015

 

24  No construction works above the level of the floor slab shall take place until details of the new accesses, removal of the existing redundant crossovers and the reinstatement of the kerb have been submitted to and approved in writing by the Local Planning Authority and a full scheme of works and the relevant highways approvals are in place.  The development shall be carried out in accordance with the approved details before the development is commenced and retained thereafter.  

 

Reason: In the interests of sustainability, accessibility, highways management, efficiency and safety in accordance DPD1 (Core Strategy) 2007 policy KP2, KP3 and CP3, Policy DM1and DM15 of the Development Management DPD 2015.

 

25  Before it is occupied or brought into use, the development hereby approved shall be carried out in a manner to ensure that 2 of the flats hereby approved comply with building regulation M4 (3) ‘wheelchair user dwellings’ and the remaining flats comply with building regulation part M4(2) ‘accessible and adaptable dwellings’.

 

Reason: To ensure the residential units hereby approved provides high quality and flexible internal layouts to meet the changing needs of residents in accordance with National Planning Policy Framework, DPD1 (Core Strategy) policy KP2, DPD2 (Development Management Document) policy DM2 and SPD1 (Design and Townscape Guide).

 

26  Prior to occupation of the development hereby approved details of the water efficient design measures set out in Policy DM2 (iv) of the Development Management Document to limit internal water consumption to 105 litres per person per day (lpd) (110 lpd when including external water consumption), including measures of water efficient fittings, appliances and water recycling systems such as grey water and rainwater harvesting shall be submitted to and approved in writing by the Local Planning Authority.  The development shall subsequently be undertaken in accordance with the approved details and retained in perpetuity.

 

Reason: To minimise the environmental impact of the development through efficient use of water in accordance with the National Planning Policy Framework, DPD1 (Core Strategy) policy KP2, DPD2 (Development Management Document) policy DM2 and SPD1 (Design and Townscape Guide).

 

27  Prior to the occupation of the flats hereby approved details of the proposed glazed screens shown on the roofspace shall be submitted and approved in writing by the Local Planning Authority.  The screens and rooftop amenity area shall subsequently be installed/provided prior to the first occupation of any of the flats hereby approved and retained in perpetuity.

 

Reason:  To safeguard the design and appearance of the building and the amenities of neighbouring residents and in the interest of the standard of accommodation and to ensure that satisfactory amenity space remains for the amenities of future occupiers, in accordance with Development Management Document Policies DM1, DM3 and DM8 and the Design and Townscape Guide, 2009 (SPD1).

 

Informative

 

Please note that the proposed development subject of this application is liable for a charge under the Community Infrastructure Levy Regulations 2010 (as amended). Enclosed with this decision notice is a CIL Liability Notice for the applicant’s attention and any other person who has an interest in the land. This contains details of the chargeable amount and how to claim exemption or relief if appropriate. There are further details on this process on the Council's website at www.southend.gov.uk/cil .

 

(c)  In the event that the planning obligation referred to in part (a) above has not been completed by 1st June 2017 the Deputy Chief Executive (Place), Director of Planning and Transport or Group Manager (Planning & Building Control) be authorised to refuse planning permission for the application on the grounds  that the development will not provide for affordable housing. As such, the proposal would be contrary to Policies KP2, KP3, CP6 and CP8.

 

Supporting documents:

 

Get the best from this site

We use simple text files called 'cookies'. Some of these cookies are essential to make our site work and others help us to improve by giving us some insight into how the site is being used. For more information, including how to turn cookies off, see more about cookies - or simply click the Continue button to use this site as normal.