Agenda item

16/02045/FULM - Rileys, 258 Leigh Road. Leigh on Sea (Leigh Ward)

Minutes:

Proposal:  Demolish existing building and erect 5 storey building incorporating 22 self-contained flats with balconies/terraces, layout parking and cycle stores at basement level, refuse store and amenity space.

Applicants:  Property Generation Services Limited

Agent:  Property Generation Services Limited

 

(a)  DELEGATED to the Deputy Chief Executive (Place), Director of Planning and Transport or Group Manager of Planning & Building Control to GRANT PLANNING PERMISSION subject to completion of a PLANNING AGREEMENT UNDER SECTION 106 of the Town and Country Planning Act 1990 (as amended) and all appropriate legislation to secure the provision of:

 

  a financial contribution for affordable housing of £187,485 (index-linked) in lieu of on-site provision, which is payable prior to occupation of the 7th dwelling

  a financial contribution towards secondary education provision of £40,315 (index-linked), specifically providing increased capacity at Futures Community College/Southchurch High School, which is payable prior to occupation of the 7th dwelling

 

(b)  The Deputy Chief Executive (Place), Director of Planning and Transport or the Group Manager (Planning & Building Control) be authorised to determine the application upon completion of the above obligation, so long as planning permission when granted and the obligation when executed, accords with the details set out in the report submitted and the conditions listed below:

 

01  The development hereby permitted shall be begun not later than 3 years beginning with the date of this permission.

 

Reason: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990

 

02  The development shall be carried out in accordance with the approved plans:  01 Site Location Plan; 02 Existing plans and elevations; 03 Proposed Site Plan & Parking Revision D; 05 Proposed Plans 0-3 Revision E; 06 Proposed fourth floor and roof plan Revision B;  Proposed elevations north and south revision C; Proposed elevations east and west revision C.

 

Reason: To ensure the development is carried out in accordance with the development plan.

 

03  Notwithstanding the details shown on the plans submitted and otherwise hereby approved, no construction works above the lower ground floor (parking) slab level shall take place until samples of the materials to be used in the construction of the external elevations of the building hereby permitted, including balconies, balustrades, screening, fenestration, have been submitted to and approved in writing by the local planning authority. Development shall be carried out in full accordance with the approved details.

 

Reason: To safeguard character and appearance of surrounding area in accordance with Policies KP2 and CP4 of the BLP and policies DM1 and DM3 of the Development Management DPD 2015

 

04  No construction works above the lower ground floor (parking) floor slab level shall take place until full details of both hard and soft landscape works have been submitted to and approved in writing by the local planning authority.  These details shall include: proposed finished levels or contours; means of enclosure (including any gates to the car parks); car parking layouts;  other vehicle and pedestrian access and circulation areas;  hard surfacing materials;  minor artefacts and structures (e.g. furniture, loggia, bollards, play equipment, refuse or other storage units, signs, lighting etc.)  Details for the soft landscape works shall include the number, size and location of the trees, shrubs and plants to be planted together with a planting specification, the management of the site (e.g. the uncompacting of the site prior to planting) and the initial tree planting and tree staking details.  The development shall be implemented in full accordance with the approved details before it is occupied or brought into use.

?

Reason: In the interests of visual amenity and the amenities of occupiers and to ensure a satisfactory standard of landscaping pursuant to Policy CP4 of the Core Strategy DPD1 with CP4 of the Core Strategy DPD1 and policies DM1 and DM3 of the Development Management DPD 2015.

 

05  A landscape management plan, including long term design objectives, management responsibilities and maintenance schedules for all landscape areas, shall be submitted to and approved by the local planning authority prior to the occupation of the development.  The landscaping of the site shall be managed in accordance with the approved plan in perpetuity.

 

Reason: In the interests of visual amenity and the amenities of occupiers and to ensure a satisfactory standard of landscaping pursuant to Policy CP4 of the Core Strategy DPD1 and Policy DM1 of the Development Management DPD 2015.

 

06  The development shall not be occupied until space has been laid out within the site in accordance with drawing No. 03 for cars to be parked and for vehicles to turn so that they may enter and leave the site in a forward gear.  The parking spaces shall be permanently retained thereafter for the parking of occupiers to the development. 

 

Reason: To ensure that adequate car parking is provided and retained to serve the development in accordance with Policies CP3 of the Core Strategy DPD1 and Policy DM15 of the Development Management DPD 2015.

 

07  No construction works above lower ground floor slab level shall take place until details of 1.8m high balcony/terrace screens to the eastern and rear splayed elevation serving flats 2 and 3 on the second, third, fourth floor and the balustrade detailing for flats 1 and 2 on the fifth floor shall have been submitted to and approved in writing by the Local Planning Authority.  The screens, as approved, shall be erected prior to first occupation of those units, and retained thereafter in perpetuity.

 

08  The development shall not be occupied until a waste management plan and service plan has been submitted to and agreed in writing by the Local Planning Authority.  The waste management and servicing of the development shall thereafter be carried out in accordance with the approved details. 

 

Reason:  to ensure that the development is satisfactorily serviced and that satisfactory waste management is undertaken in the interests of highway safety and visual amenity and to protect the character of the surrounding area, in accordance with Policies KP2 and CP3 of the Core Strategy DPD1 and  Policy DM15 of the Development Management DPD 2015.

 

09  The development shall not be occupied until details of the secure, covered cycle parking spaces to serve the residential development and cycle parking spaces have been submitted to and agreed in writing by the Local Planning Authority. The approved scheme shall be implemented prior to first occupation of the development and shall be permanently retained thereafter. 

 

Reason: To ensure that adequate cycle parking is provided and retained to serve the development in accordance with Policies CP3 of the Core Strategy DPD1 and Policy DM15 of the Development Management DPD 2015.

?

10  No development shall take place, including any works of demolition, until a Construction Method Statement has been submitted to, and approved in writing by, the local planning authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide, amongst other things, for:

 

i)  the parking of vehicles of site operatives and visitors

ii)  loading and unloading of plant and materials

iii)  storage of plant and materials used in constructing the development

iv)  the erection and maintenance of security hoarding 

v)  measures to control the emission of dust and dirt during construction

vi)  a scheme for recycling/disposing of waste resulting from demolition and construction works that does not allow for the burning of waste on site.

 

Reason: In the interests of visual amenity and the amenities of occupiers and to ensure a satisfactory standard of landscaping pursuant to Policy CP4 of the Core Strategy DPD1 with CP4 of the Core Strategy DPD1 and Policy DM1 of the Development Management DPD 2015.

 

11  No development shall take place until details of the implementation, maintenance and management of a scheme for surface water drainage works (incorporating Sustainable Urban Drainage (SuDs) Principles have been submitted to and approved by the local planning authority. The scheme shall be implemented and thereafter managed in accordance with the approved details before the development is occupied and brought into use and be maintained as such thereafter. Those details shall include:

 

i)   An investigation of the feasibility of infiltration SUDS as the preferred approach to establish if the principles of any infiltration based surface water drainage strategy are achievable across the site, based on ground conditions.  Infiltration or soakaway tests should be provided which fully adhere to BRE365 guidance to demonstrate this.  Infiltration features should be included where infiltration rates allow; 

 

ii)  Drainage plans and drawings showing the proposed locations and dimensions of all aspects of the proposed surface water management scheme.  The submitted plans should demonstrate the proposed drainage layout will perform as intended based on the topography of the site and the location of the proposed surface water management features; 

 

iii)   a timetable for its implementation; and

 

vii)  a management and maintenance plan for the lifetime of the development which shall include the arrangements for adoption by any public body or statutory undertaker, or any other arrangements to secure the operation of the sustainable drainage scheme throughout its lifetime.

 

Reason: To prevent flooding by ensuring the satisfactory storage and disposal of surface water from the site for the lifetime of the development and to prevent environmental and amenity problems arising from flooding in accordance with Policy KP2 and CP4 of the Core Strategy 2007 and area in accordance with policies  KP2 and CP4 of the Core Strategy DPD1 and  Policy DM2 of the Development Management DPD 2015.

 

12  Details of any external lighting to be installed in the development shall be submitted to and approved in writing by the local planning authority before the development is occupied or brought into use.  Development shall be carried out in accordance with the approved details before the development is occupied or brought into use.  No additional external lighting shall be installed on the building without the consent of the Local Planning Authority. 

 

Reason: In the interest of the visual amenities and character of the area, and to protect the amenities of surrounding occupiers in accordance with policies  KP2 and CP4 of the Core Strategy DPD1 and with CP4 of the Core Strategy DPD1 and Policies DM1 of the Development Management DPD 2015.

 

13  A scheme detailing how at least 10% of the total energy needs of the development will be supplied using on site renewable sources must be submitted to and agreed in writing prior to occupation of the development hereby approved by the Local Planning Authority and implemented in full prior to the first occupation of the development. This provision shall be made for the lifetime of the development.

 

Reason: In the interests of providing sustainable development in accordance with Policy KP2 of the Core Strategy and Development Management Document policy DM2.

 

14  Demolition or construction works associated with this permission shall not take place outside 08:00 hours to 18:00hours Mondays to Fridays and 08:00hours to 13:00hours on Saturdays and at no time Sundays or Bank Holidays.

 

Reason: In order to protect the amenities of occupiers of the development surrounding occupiers and to protect the character the area in accordance with policies KP2 and CP4 of the Core Strategy DPD1 and Policies DM1 and DM3 of the Development Management DPD 2015.

 

15  Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (as amended) (or any order revoking, re-enacting or modifying that Order), no structures such as canopies, fences, loggias, trellises or satellite or radio antennae shall be installed within the development or on the buildings hereby approved unless otherwise previously agreed in writing by the Local Planning Authority. 

 

Reason: In order to protect the character and visual amenities of the development and surrounding area and airport safety in accordance with policies KP2 and CP4 of the Core Strategy DPD1 and Policy DM1 of the Development Management DPD 2015.

 

16  Before the development is occupied or brought into use, the development hereby approved shall be carried out in a manner to ensure that 2 of the flats hereby approved comply with building regulation M4 (3) ‘wheelchair user dwellings’ and the remaining 20 flats comply with building regulation part M4(2) ‘accessible and adaptable dwellings’.

 

Reason: To ensure the residential units hereby approved provides high quality and flexible internal layouts to meet the changing needs of residents in accordance with National Planning Policy Framework, DPD1 (Core Strategy) policy KP2, DPD2 (Development Management Document) policy DM2 and SPD1 (Design and Townscape Guide).

 

Informatives

 

01  Please note that the development the subject of this application is liable for a charge under the Community Infrastructure Levy Regulations 2010 (as amended). A Community Infrastructure Levy (CIL) Liability Notice will be issued as soon as practicable following this decision notice. This contains details including the chargeable amount, when this is payable and when and how exemption or relief on the charge can be sought. You are advised that a CIL Commencement Notice (CIL Form 6) must be received by the Council at least one day before commencement of development. Receipt of this notice will be acknowledged by the Council. Please ensure that you have received both a CIL Liability Notice and acknowledgement of your CIL Commencement Notice before development is commenced. Most claims for CIL relief or exemption must be sought from and approved by the Council prior to commencement of the development. Charges and surcharges may apply, and exemption or relief could be withdrawn if you fail to meet statutory requirements relating to CIL. Further details on CIL matters can be found on the Council's website at www.southend.gov.uk/cil.

 

02  The applicant is reminded that this permission does not bestow compliance with other regulatory frameworks. In particular your attention is drawn to the statutory nuisance provisions within the Environmental Protection Act 1990 (as amended) and also to the relevant sections of the Control of Pollution Act 1974. The provisions apply to the construction phase and not solely to the operation of the completed development. Contact 01702 215005 for more information.

 

03  This permission is governed by a legal agreement between the applicant and the Borough Council under Section 106 of the Town and Country Planning Act 1990. The agreement relates to a financial contribution towards affordable housing and secondary education.

 

(c)  In the event that the planning obligation referred to in part (a) above has not been completed by 14th July 2017 or an extension of this time as may be agreed by the Deputy Chief Executive (Place), Director of Planning and Transport or Group Manager (Planning & Building Control), the Deputy Chief Executive (Place), Director of Planning and Transport or Group Manager (Planning & Building Control) be authorised to refuse planning permission for the application on the grounds that the development will not provide for affordable housing or education provision. As such, the proposal would be contrary to Policies KP2, KP3, CP6 and CP8.

Supporting documents:

 

Get the best from this site

We use simple text files called 'cookies'. Some of these cookies are essential to make our site work and others help us to improve by giving us some insight into how the site is being used. For more information, including how to turn cookies off, see more about cookies - or simply click the Continue button to use this site as normal.