Decision details

Capital Programme 2016/17 to 2019/20

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: No

Decisions:

The Cabinet considered a report of the Corporate Management Team setting out the proposed programme of capital projects for 2016/17 to 2019/20. This item was considered by all three Scrutiny Committees.

 

Recommended:-

 

1. That the current approved Programme for 2016/17 to 2018/19 of £129.6m, as set out in Appendix 1 of the submitted report, be noted.

 

2. That the changes to the approved Programme, as set out in Appendix 2 of the report, be approved.

 

3. That the proposed new schemes and additions to the Capital Programme for 2016/17 to 2019/20 totalling £52.7m of which £44.7m is for the General Fund and £8.0m for the Housing Revenue Account, as set out in Appendices 6 and 7 of the report, be approved.

 

4. That it be noted that, the proposed new schemes and additions, as set out in Appendices 6 and 7 of the report and other adjustments, as set out in Appendix 2 of the report, will result in a proposed capital programme of £188.1m for 2016/17 to 2019/20, as set out in Appendix 8 of the report.

 

5. That it be noted that, of the total programme of £188.1m for the period 2016/17 to 2019/20, the level of external funding supporting this programme is £65.0m.

 

6. That it be noted that a final review has been undertaken on the 2015/16 projected outturn and that the results have been included in the submitted report.

 

7. That the proposed Capital Programme for 2015/16 to 2019/20, as set out in Appendix 8 of the submitted report, be approved.

 

8. That the Capital Strategy for 2016/17 to 2019/20, be approved.

 

Reason for Decision

 

The proposed Capital Programme is compiled from a number of individual projects which either contribute to the delivery of the Council’s objectives and priorities or enhances the Council’s infrastructure. 

 

Other Options

 

The proposed Capital Programme is compiled from a number of individual projects, any of which can be agreed or rejected independently of the other projects.

 

Note:- This is a Council Budget Function, not eligible for call in by virtue of Budget and Policy Framework Procedure Rule 1.1(b)

Executive Councillor:- Woodley

Publication date: 16/02/2016

Date of decision: 11/02/2016

Decided at meeting: 11/02/2016 - Cabinet

Accompanying Documents:

 

Get the best from this site

We use simple text files called 'cookies'. Some of these cookies are essential to make our site work and others help us to improve by giving us some insight into how the site is being used. For more information, including how to turn cookies off, see more about cookies - or simply click the Continue button to use this site as normal.