Issue - meetings
Parking Procurement
Meeting: 30/08/2022 - Place Scrutiny Committee (Item 247)
Parking Procurement
Minute No. 201 (Cabinet Agenda Item No. 17 refers)
Called-in by Councillors Cox and Davidson
Additional documents:
- Restricted enclosure 2 , View reasons restricted (247/2)
- Webcast for Parking Procurement
Minutes:
The Committee considered Minute 201 of the meeting of the Cabinet held on 24th July 2022, which had been called-in for scrutiny, together with the confidential report of the Interim Executive Director (Neighbourhoods and Environment) presenting the outcomes of the invitation to Tender (ITT) process for the Parking Enforcement Services Contract Lot 1 and the Cashless Parking and Parking Permits System Contract Lot 2 and sought approval to award the Parking Enforcement Services contract (Lot 1) following the ITT process to the successful bidder and the direct award through a procurement framework agreement for the award of the Lot 2 Contract.
In response to questions regarding the one-off costs to provider A, the Interim Executive Director (Neighbourhoods & Environment) undertook to provide a full break down of the costs and the scoring criteria to the Committee.
Resolved:
That the following decisions of Cabinet be noted:
“1. That the contract be awarded to Provider A; this being the successful bidder for the Lot 1 Contract for a seven-year period with the option to extend up to a further 3 years at the Council’s discretion.
2. That authority be delegated to the Executive Director (Neighbourhoods and Environment) to liaise with Legal Services to finalise the required contract documentation and contract sealing for the Lot 1 Contract.
3. That a permanent budget increase of £300k per annum for the Lot 1 contract commencing April 2023 and that this be included as part of the 2023/24 budget setting process, be approved.
4. That one off implementation costs of £198k for the new contract funded by the Business Transformation Reserve, be approved.
5. That authority be delegated to the Executive Director (Neighbourhoods and Environment) to procure the services for Lot 2 Contract by way of direct award via a Framework Agreement, subject to the appropriate operating budget being in place.”
Note: this is an Executive Function
Cabinet Member: Cllr Wakefield
Meeting: 26/07/2022 - Cabinet (Item 201)
Parking Procurement
Confidential report of Interim Director of Highways and Parks
Additional documents:
- Restricted enclosure 5 , View reasons restricted (201/2)
- Webcast for Parking Procurement
Decision:
The Cabinet considered a report of the Interim Executive Director (Neighbourhoods and Environment) presenting the outcomes of the invitation to Tender (ITT) process for the Parking Enforcement Services Contract Lot 1 and the Cashless Parking and Parking Permits System Contract Lot 2 and sought approval to award the Parking Enforcement Services contract (Lot 1) following the ITT process to the successful bidder and the direct award through a procurement framework agreement for the award of the Lot 2 Contract.
Resolved:
1. That the contract be awarded to Provider A; this being the successful bidder for the Lot 1 Contract for a seven-year period with the option to extend up to a further 3 years at the Council’s discretion.
2. That authority be delegated to the Executive Director (Neighbourhoods and Environment) to liaise with Legal Services to finalise the required contract documentation and contract sealing for the Lot 1 Contract.
3. That a permanent budget increase of £300k per annum for the Lot 1 contract commencing April 2023 and that this be included as part of the 2023/24 budget setting process, be approved.
4. That one off implementation costs of £198k for the new contract funded by the Business Transformation Reserve, be approved.
5. That authority be delegated to the Executive Director (Neighbourhoods and Environment) to procure the services for Lot 2 Contract by way of direct award via a Framework Agreement, subject to the appropriate operating budget being in place.
Other Options:
As set out in the submitted report.
Reasons for Decisions:
As set out in the submitted report.
Note: this is an Executive Function
Eligible for call-in to: Place Scrutiny Committee
Cabinet Member: Cllr Wakefield
Minutes:
The Cabinet considered a report of the Interim Executive Director (Neighbourhoods and Environment) presenting the outcomes of the invitation to Tender (ITT) process for the Parking Enforcement Services Contract Lot 1 and the Cashless Parking and Parking Permits System Contract Lot 2 and sought approval to award the Parking Enforcement Services contract (Lot 1) following the ITT process to the successful bidder and the direct award through a procurement framework agreement for the award of the Lot 2 Contract.
Resolved:
1. That the contract be awarded to Provider A; this being the successful bidder for the Lot 1 Contract for a seven-year period with the option to extend up to a further 3 years at the Council’s discretion.
2. That authority be delegated to the Executive Director (Neighbourhoods and Environment) to liaise with Legal Services to finalise the required contract documentation and contract sealing for the Lot 1 Contract.
3. That a permanent budget increase of £300k per annum for the Lot 1 contract commencing April 2023 and that this be included as part of the 2023/24 budget setting process, be approved.
4. That one off implementation costs of £198k for the new contract funded by the Business Transformation Reserve, be approved.
5. That authority be delegated to the Executive Director (Neighbourhoods and Environment) to procure the services for Lot 2 Contract by way of direct award via a Framework Agreement, subject to the appropriate operating budget being in place.
Other Options:
As set out in the submitted report.
Reasons for Decisions:
As set out in the submitted report.
Note: this is an Executive Function
Called-in to: Place Scrutiny Committee
Cabinet Member: Cllr Wakefield