Issue - meetings

Fire Safety Report

Meeting: 09/04/2018 - Place Scrutiny Committee (Item 884)

884 Fire Safety Report pdf icon PDF 119 KB

Minute 819 (Agenda Item 10 refers)

Called in by Councillors Mulroney and Wexham

Minutes:

The Committee considered Minute 819 of Cabinet held on 13th March 2018, which had been called-in for scrutiny, together with the report of the Deputy Chief Executive (Place) setting out the interim results of the Council’s Fire Safety Review, which was established following the Grenfell Tower fire on the 14th June 2017.

 

A list of all the properties that had been contacted regarding fire safety in tall buildings owned both in the private and public sectors was circulated at the meeting for Members’ information.  In response to questions regarding the properties, the Deputy Chief Executive (Place) requested that, if any Member was aware of any tall building that was not included on the list to forward the details to him.

 

Resolved:-

 

That the following decisions of Cabinet be noted:

 

“1. That the work undertaken by the Council and South Essex Homes in respect to Fire Safety, be noted and endorsed.

 

 2. That a further update be submitted to a future meeting of the Cabinet.”

 

Note:- This is an Executive function

Executive Councillor:- Flewitt


Meeting: 13/03/2018 - Cabinet (Item 819)

819 Fire Safety Report pdf icon PDF 119 KB

Report of Deputy Chief Executive (Place) attached

Decision:

The Cabinet considered a report of the Deputy Chief Executive (Place) setting out the interim results of the Council’s Fire Safety Review, which was established following the Grenfell Tower fire on the 14th June 2017.

 

Resolved:

 

1. That the work undertaken by the Council and South Essex Homes in respect to Fire Safety, be noted and endorsed.

 

2. That a further update be submitted to a future meeting of the Cabinet.

 

Reasons for Decision:

 

As a result of the Grenfell Tower Fire the Council undertook a fundamental review of its fire safety policies and procedures and put in place appropriate resources to ensure it maintains its buildings in a safe condition whilst upgrading them where this is appropriate and practicable.

 

Other Options:

 

The Council could decide to maintain all operational properties in their current condition with fire improvement works and, where practicable, to bring them up to the requirements of the latest Building Regulations when they next undergo major alterations and/or extension. All operational buildings would still meet statutory requirements although it could be argued that the Council would not be meeting the section of the Regulatory Reform (Fire Safety) Order 2005 that requires Employers to ‘put in place, and maintain, appropriate fire safety measures’. This option has, therefore been discounted.

 

The Council could commit to bringing all operational buildings up to current Building Regulation requirements.  However, this will not always be practicable due to the construction and/or age of the building; the building may be listed on the National Heritage List for England, which could limit what works could be undertaken; or changes could be financially unviable. This option has, therefore been discounted.

 

Note: This is an Executive Function

Eligible for call-in to: Place Scrutiny Committee

Executive Councillor: Cllr Flewitt

Minutes:

The Cabinet considered a report of the Deputy Chief Executive (Place) setting out the interim results of the Council’s Fire Safety Review, which was established following the Grenfell Tower fire on the 14th June 2017.

 

Resolved:

 

1. That the work undertaken by the Council and South Essex Homes in respect to Fire Safety, be noted and endorsed.

 

2. That a further update be submitted to a future meeting of the Cabinet.

 

Reasons for Decision:

 

As a result of the Grenfell Tower Fire the Council undertook a fundamental review of its fire safety policies and procedures and put in place appropriate resources to ensure it maintains its buildings in a safe condition whilst upgrading them where this is appropriate and practicable.

 

Other Options:

 

The Council could decide to maintain all operational properties in their current condition with fire improvement works and, where practicable, to bring them up to the requirements of the latest Building Regulations when they next undergo major alterations and/or extension. All operational buildings would still meet statutory requirements although it could be argued that the Council would not be meeting the section of the Regulatory Reform (Fire Safety) Order 2005 that requires Employers to ‘put in place, and maintain, appropriate fire safety measures’. This option has, therefore been discounted.

 

The Council could commit to bringing all operational buildings up to current Building Regulation requirements.  However, this will not always be practicable due to the construction and/or age of the building; the building may be listed on the National Heritage List for England, which could limit what works could be undertaken; or changes could be financially unviable. This option has, therefore been discounted.

 

Note: This is an Executive Function

Eligible for call-in to: Place Scrutiny Committee

Executive Councillor: Cllr Flewitt

Called in to:- Place Scrutiny Committee


 

Get the best from this site

We use simple text files called 'cookies'. Some of these cookies are essential to make our site work and others help us to improve by giving us some insight into how the site is being used. For more information, including how to turn cookies off, see more about cookies - or simply click the Continue button to use this site as normal.