Agenda item
Capital Programme 2018/19 to 2021/22
- Meeting of Cabinet, Tuesday, 13th February, 2018 2.00 pm (Item 737.)
- View the background to item 737.
Minutes:
The Cabinet considered a report of the Corporate Management Team setting out the proposed programme of capital projects for 2018/19 to 2021/22. This item had been considered by all three Scrutiny Committees.
Recommended:-
1. That the current approved Programme for 2018/19 to 2021/22 of £166.5m, as set out in Appendix 1 to the submitted report, be noted.
2. That the changes to the approved Programme as set out in Appendix 2 to the submitted report, be approved.
3. That the proposed new schemes and additions to the Capital Programme for 2018/19 to 2019/20 totalling £20.1m, as set out in Appendices 6 and 7 to the submitted report, be approved.
4. That the proposed schemes subject to external funding approval for the period 2018/19 to 2021/22 totalling £19.0m, as set out in Appendices 2 and 7 of the submitted report be approved.
5. That it be noted that the proposed new schemes and additions as set out in Appendices 6 and 7 to the submitted report, and other adjustments as set out in Appendix 2 to the report will result in a proposed capital programme of £192.0m for 2018/19 to 2021/22 set out in Appendix 8.
6. That it be noted that of the total programme of £192.0m for the period 2018/19 to 2021/22, the level of external funding supporting this programme is £75.0m, as set out in paragraph 9.1 of the submitted report.
7. That it be noted that a final review has been undertaken on the 2017/18 projected outturn and that the results have been included in the submitted report.
8. That the proposed Capital Programme for 2017/18 to 2021/22, as set out in Appendix 8 to the submitted report, be approved.
9. That the Capital Strategy for 2018/19 to 2021/22, as set out in Appendix 9 to the submitted report, be approved.
Reason for recommendation
The proposed Capital Programme is compiled from a number of individual projects which either contribute to the delivery of the Council’s objectives and priorities or enhances the Council’s infrastructure.
Other Options
The proposed Capital Programme is compiled from a number of individual projects, any of which can be agreed or rejected independently of the other projects.
Note:- This is a Council Budget Function, not eligible for call in by virtue of Budget and Policy Framework Procedure Rule 1.1(b)
Executive Councillor:- Lamb
Supporting documents:
- Report of Corporate Management Team, item 737. PDF 147 KB
- CE27 Appendix 1 - Approved Capital Programme November 2017, item 737. PDF 155 KB
- CE27 Appendix 2 - Summary of Changes to the Capital Programme, item 737. PDF 67 KB
- CE27 Appendix 3 - Virements Between Approved Schemes, item 737. PDF 14 KB
- CE27 Appendix 4 - Re-profiles Between Years, item 737. PDF 24 KB
- CE27 Appendix 5 - New External Funding, item 737. PDF 67 KB
- CE27 Appendix 5a - LTP3 - Capital Actions and Allocations, item 737. PDF 185 KB
- CE27 Appendix 5b - Highways Capital Programme 2018-19, item 737. PDF 199 KB
- CE27 Appendix 6 - Proposed New Schemes and Additions to the Capital Programme, item 737. PDF 80 KB
- CE27 Appendix 7 - Proposed New Schemes and Additions - descriptions, item 737. PDF 457 KB
- CE27 Appendix 8 - Amended Capital Programme 2018-19 to 2021-22, item 737. PDF 167 KB
- CE27 Appendix 9 - Capital Strategy 2018-19 to 2021-22, item 737. PDF 307 KB