Minutes:
The Cabinet considered a report of the Strategic Director (Finance and Resources) setting out a draft programme of capital investment for the period 2019/20 to 2023/24.
Resolved:
1. That the current approved programme for 2019/20 to 2021/22 of £153.1m as set out in Appendix 1 to the submitted report, be noted.
2. That the Capital Investment Strategy for 2019/20 to 2023/24, as set out in Appendix 2 to the report, be approved.
3. That the following be approved:
(i) New schemes and additions to the Capital Investment Programme for the period 2019/20 to 2023/24 totalling £14.5m for the General Fund and £20.8m for the Housing Revenue Account (Appendix 6 to the submitted report);
(ii) Schemes subject to external funding approval for the period 2019/20 to 2020/21 totalling £3.0m (Appendix 6 to the report);
(iii) Schemes subject to viable business cases for the period 2019/20 to 2021/22 totalling £48.6m (Appendices 6 and 7 to the report).
4. That it be noted that the changes to the approved Programme will result in a proposed Capital Investment Programme of £177.0m for 2019/20 to 2023/24, as set out in Appendix 7 to the report, of which £70.7m is supported by external funding.
5. That it be noted that a final review is being undertaken on the 2018/19 projected outturn and the results will be included in the report to Cabinet on 12 February 2019.
Reasons for decision:
The Capital Investment Programme is compiled from a number of individual projects which either contribute to the delivery of the Council’s ambition and desired outcomes or enhance the Council’s infrastructure.
Other options:
The Capital Investment Programme is compiled from a number of individual projects, any of which can be agreed or rejected independently of the other projects.
Note: This is an Executive Function save that approval of the final budget following Cabinet on 12 February 2019 is a Council Function.
Referred direct to all three Scrutiny Committees
Cabinet Member: Cllr Lamb
Supporting documents:
- Report of Strategic Director (Finance and Resources), item 610. PDF 141 KB
- Appendix 1 - Approved Capital Investment Programme - November 18, item 610. PDF 220 KB
- Appendix 2 - Capital Investment Strategy 2019-20 to 2023-24, item 610. PDF 169 KB
- Annex 1 to Appendix 2 - Capital Investment Policy, item 610. PDF 68 KB
- Annex 2 to Appendix 2 - Capital Investment Strategy - links to other corporate strategies and plans, item 610. PDF 32 KB
- Annex 3 to Appendix 2 - Specific risks and their proposed mitigation, item 610. PDF 44 KB
- Annex 4 to Appendix 2 - Monitoring lifecycle for capital programme expenditure, item 610. PDF 232 KB
- Annex 5 to Appendix 2 - Gateway Review process, item 610. PDF 46 KB
- Annex 6 to Appendix 2 - Key Project Stages, item 610. PDF 62 KB
- Annex 7 to Appendix 2 - Policies re funding capital expenditure and investment, item 610. PDF 51 KB
- Appendix 3 - Virements Between Approved Schemes, item 610. PDF 16 KB
- Appendix 4 - Re-profiles Between Years, item 610. PDF 19 KB
- Appendix 5 - New External Funding, item 610. PDF 9 KB
- Appendix 6 - Proposed New Schemes and Additions - descriptions, item 610. PDF 213 KB
- Appendix 7 - Summary of Changes to Approved Capital Investment Programme, item 610. PDF 24 KB
- Appendix 8 - Amended Capital Investment Programme 2019-20 to 2023-24, item 610. PDF 343 KB