Agenda item

18/00679/AMDT - 411-415 Sutton Road, Southend on Sea (Victoria Ward)

Minutes:

Proposal:  Application to vary condition 02 (Approved Plans), condition 04 (Landscaping) and condition 05 (Parking) replacing plan number 16.563 200 P5 (Proposed site plan and street scene) with plan number 16.563 200 P6 (Proposed site plan and street scene), and replacing plan number 2244-17 rev 3 (Soft landscaping – planting) with 2244-17 rev 8 (Soft landscaping – planting)  (Minor Material Amendment to planning permission 17/00821/AMDT dated 06.12.2017)

Applicant:  Dove Jeffrey Homes Ltd

Agent:  FRONT Architecture Ltd

 

Resolved:  (a)  That the Deputy Chief Executive (Place), Director of Planning and Transport or Group Manager of Planning & Building Control to GRANT PLANNING PERMISSION subject to completion of a PLANNING AGREEMENT UNDER SECTION 106 of the Town and Country Planning Act 1990 (as amended) and all appropriate legislation to seek the following:

 

  A minimum of 9 units of affordable rented housing units (20% of overall provision) comprising 2x1 bed and 7x2 bed units.

  Traffic Regulation Order contribution of £4,000

  Provision of Travel Packs for residents.

  Retail Travel Plan. 

 

(b)  The Deputy Chief Executive (Place), Director for Planning and Transport or the Group Manager (Planning & Building Control) be authorised to determine the application upon completion of the above obligation, so long as planning permission when granted and the obligation when executed, accords with the details set out in the report submitted and the conditions listed below:

 

01  The development shall be carried out in accordance with the approved plans:

 

Location plan 001

16.563 200 P6 Proposed site plan and street scene

2244-17 rev 8 Soft landscaping – planting

FRNT_16.563_201_P4 Block A floor plans

FRNT_16.563_202_P4 Block B floor plans

FRNT_16.563_203_P4 Block C Floor Plans

FRNT_16.563_204_P4 Block A elevations

FRNT_16.563_205_P4 Block B elevations

FRNT_16.563_206_P4   Block C elevations

FRNT_16.563_208_P4 Proposed overview floor plans

 

Reason: To ensure the development is carried out in accordance with the development plan.

 

02  Materials to be used in the construction of the external elevations of the building hereby permitted, including balconies, balustrades, screening, fenestration, front porches and hoods, shall be in accordance with details approved under application18/00053/AD or other details as submitted to the local planning authority and approved in writing before the relevant unit is occupied.

 

Reason: To safeguard character and appearance of surrounding area in accordance with Policies KP2 and CP4 of the Core Strategy 2007, Policy DM1 and DM3 of the Development Management Document 2015 and the Design and Townscape Guide 2009

 

03  Hard and Soft Landscaping shall be carried out in accordance with the approved plan No 2244-17 rev 8. Hard Landscaping shall be completed prior to first occupation of the development and soft landscaping/planting shall be completed within the planting season following first occupation of the development. (or within any other time limit agreed in writing with the local planning authority). If any trees are removed or found to be dying, severely damaged or diseased within 5 years of planting them, they must be replaced with trees of a similar size and species.

 

Reason: In the interests of visual amenity and the amenities of occupiers and to ensure a satisfactory standard of landscaping pursuant to Policy CP4 of the Core Strategy (2007) and Policy DM1 and DM3  of the Development Management Document 2015.

 

04  The development shall not be occupied until space has been laid out within the site in accordance with drawing 16.563 200 P6 for cars to be parked and for the loading and unloading of vehicles and for vehicles to turn so that they may enter and leave the site in forward gear.  The parking spaces shall be permanently retained thereafter for the parking of occupiers, staff and visitors to the development. 

 

Reason: To ensure that adequate car parking is provided and retained to serve the development in accordance with Policies CP3 of the Core Strategy (2007) and Policy DM15 of the Development Management Document 2015.

 

05  The development shall not be occupied until a car park management plan for the development has been submitted to and agreed in writing by the Local Planning Authority.  The development shall only be occupied in accordance with the agreed management plan.

 

Reason: To ensure that the car parking is satisfactorily managed in the interests of traffic management and highway safety in accordance with Policies KP2 and CP3 of the Core Strategy (2007) and Policy DM15 of the Development Management Document (2015)

 

06  The development shall not be occupied until a waste management plan and service plan has been submitted to and agreed in writing by the Local Planning Authority. The waste management and servicing of the development shall thereafter be carried out only in accordance with the approved details. 

 

Reason:  To ensure that the development is satisfactorily serviced and that satisfactory waste management is undertaken in the interests of highway safety and visual amenity and to protect the character of the surrounding area, in accordance with Policies KP2 and CP3 of the Core Strategy (2007)  and  Policy DM15 of the Development Management Document (2015).

 

07  Secure, covered cycle parking shall be provided to serve the residential development and the retail/commercial unit, in accordance with the details approved under application 18/00053/AD or other details that may be submitted to the local planning authority and approved in writing, and each part of the development shall not be occupied until the approved facilities are available for the use of the occupiers and users of the respective parts of the development, and shall be retained thereafter. 

 

Reason: To ensure that adequate cycle parking is provided and retained to serve the development in accordance with Policies CP3 of the Core Strategy (2007) DPD1 and Policy DM15 of the Development Management Document (2015).

 

08  Construction shall be carried out in accordance with the Construction Method Statement approved under application 17/00883/AD unless otherwise agreed in writing with the Local Planning Authority. The approved Statement shall be adhered to throughout the construction period.

 

Reason: In the interests of visual amenity and to protect the amenities of occupiers of the development and surrounding occupiers pursuant to Policies CP4 of the Core strategy (2007) and policies DM1 and DM3 of the Development Management Document (2015).

 

09  Before the retail use hereby permitted begins a scheme for the installation of equipment to control the emission of fumes and smell from the premises shall be submitted to and approved in writing by the Local Planning Authority. The scheme as approved shall be implemented before the retail unit is occupied. All equipment installed as part of the scheme shall thereafter be operated and maintained in accordance with the manufacturer's instructions.

 

Reason: In order to protect the amenities of occupiers of the development and surrounding occupiers and to protect the character and visual amenities of the area in accordance with policies Policies KP2 and CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015)

 

10  With reference to BS4142, the noise rating level arising from all plant and extraction/ventilation equipment shall be at least 5dB(A) below the prevailing background at 3.5 metres from ground floor façades and 1 metre from all other façades of the nearest noise sensitive property with no tonal or impulsive character. 

 

Reason: In order to protect the amenities of occupiers of the development surrounding occupiers and to protect the character and visual amenities of the area in accordance with policies Policies KP2 and CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015.)

 

11  The retail use hereby permitted shall not be open to customers outside the following times: 07:00 to 23:00 hours on any day.

 

Reason: In order to protect the amenities of occupiers of the development surrounding occupiers and to protect the character and amenities of the area in accordance with policies Policies KP2 and CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015)

 

12  No deliveries or refuse collection shall be taken at or despatched from the retail unit outside the hours of 07:00-19:00hours Mondays to Fridays and 08:00-13:00hours on Saturdays nor at any time on Sundays, Bank or Public Holidays.

 

Reason: In order to protect the amenities of occupiers of the development surrounding occupiers and to protect the character and amenities of the area in accordance with policies Policies KP2 and CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015).

 

13  The development shall be carried out in accordance with the assessment of contamination and mitigation measures approved further to application ref 17/00953/AD or other details that may have been submitted to the local planning authority and approved in writing before the development is occupied or brought into use. If, during the course of development, any further contamination is found which has not been identified in the site investigation, additional measures for the remediation of this source of contamination shall be submitted to and approved in writing by the local planning authority before the development is brought into use. The remediation of the site shall incorporate the approved additional measures before the development is brought into use.

 

Reason: To ensure that any contamination on the site is identified and treated so that it does not harm anyone who uses the site in the future, and to ensure that the development does not cause pollution to Controlled Waters in accordance with Core Strategy (2007) policy KP2 and Policies DM1 and DM14 of the Development Management Document (2015).

 

14  The development shall be carried out in accordance with the details of the implementation, maintenance and management of a scheme for surface water drainage works that have been approved in application 18/00053/AD or other details that may have been submitted to the local planning authority and approved in writing. The scheme shall be implemented in accordance with the approved details before the development is occupied and shall be maintained as such thereafter.

 

Reason: To prevent flooding by ensuring the satisfactory storage and disposal of surface water from the site for the lifetime of the development and to prevent environmental and amenity problems arising from flooding in accordance with Policy KP2  and CP4 of the Core Strategy (2007) and area in accordance with Policy DM2 of the Development Management Document (2015).

 

15  Details of any external lighting shall be submitted to and approved in writing by the local planning authority before the retail use hereby permitted begins and residential apartments are occupied. The development shall be carried out in accordance with the approved details.  No additional external lighting shall be installed on the building without the consent of the Local Planning Authority. 

 

Reason: In the interest of the visual amenities and character of the area, and to protect the amenities of surrounding occupiers in accordance with policies  Policies KP2 and CP4 of the Core Strategy (2007) and Policies DM1 of the Development Management Document (2015).

 

16  The development shall be carried out in accordance with the scheme for protecting the proposed dwellings from noise from road traffic approved in application 18/00053/AD, unless otherwise agreed in writing by the Local Planning Authority. The agreed noise mitigation measures shall be installed prior to first occupation of the dwellings and retained at all times thereafter.

 

Reason: In order to the protect the amenities of future residents in accordance with policies KP2 and CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015).

 

17  Demolition or construction works shall not take place outside 07:30hours to 18:00hours Mondays to Fridays and 08:00hours to 13:00hours on Saturdays nor at any time on Sundays or Bank Holidays.

 

Reason: In order to protect the amenities of occupiers of the development surrounding occupiers and to protect the character the area in accordance with policies Policies KP2 and CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015).

 

18  Landscape management of the development, including management responsibilities and maintenance for all landscape areas shall be carried out only in accordance with details approved under application 17/00884/AD or other details that have been previously submitted to the local planning authority and approved in writing. 

 

Reason: In the interests of visual amenity and the amenities of occupiers and to ensure a satisfactory standard of landscaping pursuant to Policy CP4 of the Core Strategy (2007) and Policy DM1 of the Development Management Document (2015).

 

19  The development shall be carried out in accordance with the scheme of Photovoltaic cells approved in application 18/00053/AD or other details that have previously been submitted to the local planning authority and approved in writing. The approved details shall be installed prior to first occupation of the dwellings and brought into use on first occupation of the development.

 

Reason: To ensure the development maximises the use of renewable and recycled energy, water and other resources, in accordance with Policy KP2 of the Core Strategy (2007) and Policy DM2 of the Development Management Document 2015.

 

20  Prior to the installation of any shopfront, the details of the design, materials, glazing, doors, shutters, signage and lighting shall be submitted to and approved in writing by the Local Planning Authority. The retail unit development shall be carried out in accordance with the approved details before it is occupied and permanently retained thereafter.  

 

Reason: In order to protect the character and visual amenities of the area in accordance with policies KP2 and CP4 of the Core Strategy (2007) and Policy DM1 of the Development Management Document 2015.

 

21  Notwithstanding the provisions of the Town and Country Planning (Control of Advertisements) Regulations 2007, or any order revoking and re-enacting that Order with or without modification, no advertisement shall be displayed on the building without the prior written consent of the Local Planning Authority. 

 

Reason: In the interest of the visual amenities of the area in accordance with policies  KP2 and CP4 of the Core Strategy (2007) and  Policy DM1 and DM13 of the Development Management Document (2015).

 

22  Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (as amended) (or any order revoking, re-enacting or modifying that Order), no structures such as canopies, fences, loggias, trellises or satellite or radio antennae shall be installed within the development or on the buildings unless otherwise agreed in writing by the Local Planning Authority. 

 

Reason: In order to protect the character and visual amenities of the development and surrounding area in accordance with policies KP2 and CP4 of the Core Strategy (2007) and Policy DM1 of the Development Management Document (2015)

 

23  The commercial floorspace hereby approved shall only be occupied for uses falling within Use Class A1 retail and shall not be used for any other purpose and for no other purpose including any within Classes A2, A3, A4 and A5, C3 or D1 of the Town and Country Planning (Use Classes) Order 1987 as amended (or any statutory modification or re-enactment or replacement thereof (as the case may be) for the time being in force).  The hereby approved Use Class A1 retail floorspace shall also not be used for any alternative uses otherwise permitted under the provisions of any development order made under Section 59 of the Town and Country Planning Act 1990 (or any order revoking or re-enacting that Order).

 

Reason: In order to protect the amenities of occupiers of the development surrounding occupiers and to protect the character and amenities of the area in accordance with Policies KP2 and CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015).

 

24  The development shall be carried out in accordance with the Method Statements for Tree Protection and Tree Works approved under application 17/00885/AD unless otherwise agreed in writing by the Local Planning Authority. 

 

Reason In the interests of amenity, to protect existing trees and to ensure a satisfactory standard of landscaping pursuant to Policy CP4 of the Core Strategy (2007)  and policy DM1 of the Development Management Document (2015)

 

25  The development shall not be occupied until new accesses, removal of the existing redundant crossovers and street furniture, loading bays, on street car parking spaces and public realm improvements in accordance with details approved under application 17/00974/AD, or other details to have previously been submitted to the local planning authority and approved in writing, have been implemented in full and (prior to this) the Council as Highways Authority has approved in writing a full scheme of highways works and the relevant associated highways approvals are in place.

 

Reason: In the interests of sustainability, accessibility, highways management, efficiency and safety in accordance Core Strategy (2007) policies KP2, KP3 and CP3 and policies  DM1and DM15 of the Development Management Document (2015)

 

Informatives

 

01  The applicant is reminded that this permission does not bestow compliance with other regulatory frameworks. In particular your attention is drawn to the statutory nuisance provisions within the Environmental Protection Act 1990 (as amended) and also to the relevant sections of the Control of Pollution Act 1974. The provisions apply to the construction phase and not solely to the operation of the completed development. Contact 01702 215005 for more information.

 

02  For further guidance on the control of odour and noise from ventilation systems you are advised to have regard to – Guidance on the Control of Odour and Noise from Commercial Kitchen Exhaust Systems published by DEFRA. This can be downloaded free from www.DEFRA.Gov.UK

 

03  The applicant is reminded that this permission does not bestow compliance with the Licensing Act 2003. Applicants should contact the Council’s Licensing Team for more advice on 01702 215005.

 

04  Anglian Water has assets close to or crossing this site or there are assets subject to an adoption agreement. Therefore the site layout should take this into account and accommodate those assets within either prospectively adoptable highways or public open space. If this is not practicable then the sewers will need to be diverted at the developers cost under Section 185 of the Water Industry Act 1991 or, in the case of apparatus under an adoption agreement, liaise with the owners of the apparatus. It should be noted that the diversion works should normally be completed before development can commence.

 

05  An application to discharge trade effluent must be made to Anglian Water and must have been obtained before any discharge of trade effluent can be made to the public sewer. Anglian Water recommends that petrol / oil interceptors be fitted in all car parking/washing/repair facilities. Failure to enforce the effective use of such facilities could result in pollution of the local watercourse and may constitute an offence. Anglian Water also recommends the installation of a properly maintained fat traps on all catering establishments. Failure to do so may result in this and other properties suffering blocked drains, sewage flooding and consequential environmental and amenity impact and may also constitute an offence under section 111 of the Water Industry Act 1991.

 

06  There is clear evidence that the installation of Automatic Water Suppression Systems (AWSS) can be effective in the rapid suppression of fires. Essex County Fire and Rescue Service (ECFRS) therefore uses every occasion to urge building owners and developers to consider the installation of AWSS. ECFRS are ideally placed to promote a better understanding of how fire protection measures can reduce the risk of life, business continuity and limit the impact of fire on the environment and local economy. Even where not required under Building Regulation’s guidance, ECFRS would strongly recommend a risk base approach to the inclusion of AWSS, which can substantially reduce the risk to life and of property loss. We would also encourage developers to use them to allow design freedom, where it can be demonstrated that there is an equivalent level of safety and that the functional requirements of the regulations are met. 

 

07  The applicant is reminded that additional water supplies for fire fighting may be necessary for this development. The applicant is urged to contact the Water Technical Officer at Service Headquarters tel 01376 576342

 

08  Please note that the proposed development subject of this application is liable for a charge under the Community Infrastructure Levy Regulations 2010 (as amended). Enclosed with this decision notice is a CIL Liability Notice for the applicant’s attention and any other person who has an interest in the land. This contains details of the chargeable amount and how to claim exemption or relief if appropriate. There are further details on this process on the Council's website at www.southend.gov.uk/cil.

 

09  In relation to Condition 26; you are advised to contact Highways Engineer – Martin Warren; (Tel: 01702 215003) to discuss the requisite Highways Licence/Agreements under the Highways Act 1980. You are advised that a Highways Licence/Agreement needs to be in place before any works are carried out to the public highway and any works to public transport infrastructure (e.g. bus stops) will need to be carried out by a Council approved contractor.

 

10  You should be aware that in cases where damage occurs during construction works to the highway in implementing this permission that Council may seek to recover the cost of repairing public highways and footpaths from any party responsible for damaging them. This includes damage carried out when implementing a planning permission or other works to buildings or land. Please take care when carrying out works on or near the public highways and footpaths in the borough.

 

(c)  In the event that the planning obligation referred to in part 10(a) above has not been completed by 27th September 2018 or a later date that has been agreed in writing by the local planning authority, the Deputy Chief Executive (Place), Director of Planning and Transport or Group Manager (Planning & Building Control) be authorised to refuse planning permission for the application on the grounds  that the development will not provide for affordable housing and this would fail to provide an appropriate mix of housing contrary to the objectives of Policies KP1, KP2, KP3, CP4 and CP8 of the Southend-on-Sea Core Strategy (2007), Policies DM1 and DM7 of the Southend-on-Sea Development Management Document (2015) the Southend Central Area Action Plan (2018).

 

 The Local Planning Authority has acted positively and proactively in determining this application by assessing the proposal against all material considerations, including planning policies and any representations that may have been received and subsequently determining to grant planning permission in accordance with the presumption in favour of sustainable development, as set out within the National Planning Policy Framework.  The detailed analysis is set out in a report on the application prepared by officers.

Supporting documents:

 

Get the best from this site

We use simple text files called 'cookies'. Some of these cookies are essential to make our site work and others help us to improve by giving us some insight into how the site is being used. For more information, including how to turn cookies off, see more about cookies - or simply click the Continue button to use this site as normal.