Agenda item

19/02036/FUL - 228 Highlands Boulevard - Leigh-on-Sea (West Leigh Ward)

Minutes:

Proposal:Erection of dwelling house following demolition of existing (part-retrospective)

Applicant:  Mr Richard Chalmers

Agent: Mr Oliver Beacham

 

Resolved:-

 

That PLANNING PERMISSION be GRANTED subject to the following conditions:

 

01       The development hereby permitted shall begin not later than three years from the date of this decision.

 

Reason: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.

 

02       The development hereby permitted shall be carried out in accordance with the following approved plans: 17.102-01, 17.102-02, 17.102-03, 17.102-04, 17.102-05, 17.102-06, 17.102-07, 17.102-08 D, 17.102-09 D, 17.102-10 D, 17.102-11 D, 17.102-12 D, 17.102-13 D, 17.102-14 D, 17.102-15 D, 17.102-16 D, 17.102-17 D.

 

Reason: To ensure that the development is carried out in accordance with the provisions of the Development Plan.

 

03       The roof of the building/extension hereby approved shall not be used as a balcony, roof garden or similar amenity area or for any other purpose unless otherwise agreed in writing by the local planning authority. The roof can however be used for the purposes of maintenance or to escape in an emergency.

 

Reason: To protect the privacy and environment of people in neighbouring residential properties, in accordance with the National Planning Policy Framework, Policies KP2 and CP4 of the Southend-on-Sea Core Strategy (2007), Policies DM1 and DM3 of the Southend-on-Sea Development Management Document (2015) and the advice contained within the Southend-on-Sea Design and Townscape Guide (2009).

 

04       The development shall only be carried out using external materials, samples and the specifications of which shall have previously been submitted to and approved in writing by the local planning authority. The development shall be carried out only in accordance with the approved details before it is occupied.

 

Reason: In the interests of visual amenity and to ensure that the appearance of the buildings makes a positive contribution to the character and appearance of the area, further to the National Planning Policy Framework, Policies KP2 and CP4 of the Southend-on-Sea Core Strategy (2007), Policies DM1 and DM3 of the Southend-on-Sea Development Management Document (2015) and the advice contained within the Southend-on-Sea Design and Townscape Guide (2009).

 

05       Hard and soft landscape works and boundary treatments shall only be carried out at the site in accordance with details to have been previously submitted to and approved in writing by the local planning authority. The approved boundary treatments and hard landscaping shall be installed prior to first occupation of the development and the soft landscaping works within the first planting season following first occupation of the development.

 

Reason: In the interests of visual amenity and neighbour amenities and to ensure that the appearance of the building makes a positive contribution to the character and appearance of the area, further to the National Planning Policy Framework, Policies KP2 and CP4 of the Core Strategy (2007), Policies DM1 and DM3 of the Development Management Document (2015) and the advice contained within the Design and Townscape Guide (2009).

 

06       Notwithstanding the details shown on the approved plans, the proposed first floor flank windows, and second floor rooflights, on the north and south elevations shall only be glazed in obscure glass (the glass to be obscure to at least Level 4 on the Pilkington Levels of Privacy) and fixed shut, except for any top hung fan light which shall be a minimum of 1.7 metres above internal floor level and shall be retained as such in perpetuity thereafter.

 

Reason: To protect the privacy and environment of people in neighbouring residential properties, in accordance with the National Planning Policy Framework, Policies KP2 and CP4 of the Southend-on-Sea Core Strategy (2007), Policies DM1 and DM3 of the Southend-on-Sea Development Management Document (2015) and the advice contained within the Southend-on-Sea Design and Townscape Guide (2009).

 

07       Prior to the first occupation of the dwelling hereby approved the car parking and turning area identified on the plans hereby approved shall be provided and made available for use by the occupants of the proposed dwelling and their visitors and shall be retained as such in perpetuity thereafter.

 

Reason: To ensure the provision of adequate car parking in accordance with the National Planning Policy Framework, Policies KP2 and CP3 of the Southend-on-Sea Core Strategy (2007), Policy DM15 of the Southend-on-Sea Development Management Document (2015) and the advice contained within the Southend-on-Sea Design and Townscape Guide (2009).

 

08       Construction hours for the development hereby approved shall be restricted to 8am to 6pm Monday to Friday, 8am to 1pm on Saturdays and not at all on Sundays or Bank Holidays.

 

Reason: To protect the environment of people in neighbouring residential properties, in accordance with the National Planning Policy Framework, Policies KP2 and CP4 of the Southend-on-Sea Core Strategy (2007), Policies DM1 and DM3 of the Southend-on-Sea Development Management Document (2015) and the advice contained within the Southend-on-Sea Design and Townscape Guide (2009).

09       Notwithstanding the provisions of Classes A, B and E of Part 1 of Schedule 2 to the Town and Country Planning General Permitted Development Order 2015 (or any statutory amendment, modification or re-enactment or replacement thereof (as the case may be) for the time being in force), no extensions shall be erected at the building hereby approved without the receipt of express planning permission.

 

Reason: To safeguard the amenities of neighbours and the character and appearance of the surrounding area in accordance with the National Planning Policy Framework, Policies KP2 and CP4 of the Southend-on-Sea Core Strategy (2007), Policies DM1 and DM3 of the Southend-on-Sea Development Management Document (2015) and the advice contained within the Southend-on-Sea Design and Townscape Guide (2009).

 

10       The development hereby approved shall be carried out in a manner to ensure the dwelling complies fully with Building Regulation M4(2) 'accessible and adaptable dwellings' before it is occupied.

 

Reason: To ensure the residential units hereby approved provides high quality and flexible internal layouts to meet the changing needs of residents in accordance with the National Planning Policy Framework, Policy KP2 of the Southend-on-Sea Core Strategy (2007), Policy DM2 of the Southend-on-Sea Development Management Document (2015) and the advice contained within the Southend-on-Sea Design and Townscape Guide (2009).

 

11       A scheme detailing how at least 10% of the total energy needs of the dwelling will be supplied using on site renewable sources must be submitted to and agreed in writing by the Local Planning Authority and implemented in full prior to the first occupation of the dwelling.

 

Reason: In the interests of providing sustainable development in accordance with Policy KP2 of the Southend-on-Sea Core Strategy (2007), and Policy DM2 of the Southend-on-Sea Development Management Document (2015).

 

12       The development hereby approved shall incorporate water efficient design measures set out in Policy DM2 (iv) of the Development Management Document to limit internal water consumption to 105 litres per person per day (lpd) (110 lpd when including external water consumption), including measures of water efficient fittings, appliances and water recycling systems such as grey water and rainwater harvesting.

 

Reason: To minimise the environmental impact of the development through efficient use of water in accordance with the National Planning Policy Framework, Policy KP2 of the Southend-on-Sea Core Strategy (2007), Policy DM2 of the Southend-on-Sea Development Management Document (2015) and the advice contained within the Southend-on-Sea Design and Townscape Guide (2009).

 

 

The Local Planning Authority has acted positively and proactively in determining this application by assessing the proposal against all material considerations, including planning policies and any representations that may have been received and subsequently determining to grant planning permission in accordance with the presumption in favour of sustainable development, as set out within the National Planning Policy Framework. The detailed analysis is set out in a report on the application prepared by officers.

 

Informatives

 

01.      You should be aware that in cases where damage occurs during construction works to the highway in implementing this permission that Council may seek to recover the cost of repairing public highways and footpaths from any party responsible for damaging them. This includes damage carried out when implementing a planning permission or other works to buildings or land. Please take care when carrying out works on or near the public highways and footpaths in the borough.

 

02.      Notwithstanding the approved plans, no permission is hereby granted for the use of white cedar vertical Hardie plank cladding or white composite cladding on the proposed development.

 

03.      Please note that the development the subject of this application is liable for a charge under the Community Infrastructure Levy (CIL) Regulations 2010 (as amended) and it is the responsibility of the landowner(s) to ensure they have fully complied with the requirements of these regulations. A failure to comply with the CIL regulations in full can result in a range of penalties. For full planning permissions, a CIL Liability Notice will be issued by the Council as soon as practicable following this decision notice. For general consents, you are required to submit a Notice of Chargeable Development (Form 5) before commencement; and upon receipt of this, the Council will issue a CIL Liability Notice including details of the chargeable amount and when this is payable. If you have not received a CIL Liability Notice by the time you intend to commence development it is imperative that you contact S106andCILAdministration@southend.gov.uk to avoid financial penalties for potential failure to comply with the CIL Regulations 2010 (as amended). If the chargeable development has already commenced, no exemption or relief can be sought in relation to the charge and a CIL Demand Notice will be issued requiring immediate payment. Further details on CIL matters can be found on the Planning Portal (www.planningportal.co.uk/info/200136/

policy_and_legislation/70/community_infrastructure_levy) or the Council's website (www.southend.gov.uk/cil).

Supporting documents:

 

Get the best from this site

We use simple text files called 'cookies'. Some of these cookies are essential to make our site work and others help us to improve by giving us some insight into how the site is being used. For more information, including how to turn cookies off, see more about cookies - or simply click the Continue button to use this site as normal.