Agenda item

19/02289/FUL - Development Land Underwood Square, Leigh-on-Sea (West Leigh Ward)

Minutes:

Proposal: Erect 4no two storey semi-detached dwelling houses with associated landscaping and amenities, layout parking to front and form vehicular accesses on to Underwood Square (Amended Proposal)

Applicant: Mr G Newton

Agent: Steven Kearney of SKArchitects

 

Mr Burry spoke as an objector to the application. There was no respondent.

 

Resolved:-

 

That PLANNING PERMISSION be GRANTED subject to the following conditions:

 

01       The development hereby permitted shall begin not later than three years of the date of this decision

 

Reason: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990

 

 

02       The development hereby permitted shall be carried out in accordance with the following approved plans 385-P700, 385-P701, 385-P702, 385-P703A, 385-P704, GBU 2113

 

Reason: To ensure that the development is carried out in accordance with the Development Plan.

 

 

03       Notwithstanding the details shown on the plans submitted and otherwise hereby approved, no construction works other than demolition and construction up to ground floor slab level shall take place until product details of the materials to be used on all the external elevations, including walls, gable, roof, fascia and soffits, windows and doors, dormer windows, canopy, chimney, boundary walls and fences, driveway including parking area have been submitted to and approved in writing by the local planning authority.  The development shall only be carried out in accordance with the approved details before it is brought into use.

 

Reason: To safeguard the visual amenities of the area, in accordance with the National Planning Policy Framework (2019) Core Strategy (2007) policy KP2 and CP4, Development Management Document (2015) Policy DM1 and advice contained within the Southend Design and Townscape Guide (2009).  

 

 

04       The first floor windows in the north and south elevations of the approved dwellings shall only be glazed in obscure glass (the glass to be obscure to at least Level 4 on the Pilkington Levels of Privacy, or such equivalent as may be agreed in writing with the local planning authority) and fixed shut up to a height of not less than 1.7m above first floor level before the occupation of the dwellings hereby approved and shall be retained as such in perpetuity.  In the case of multiple or double glazed units at least one layer of glass in the relevant units shall be glazed in obscure glass to at least Level 4.

 

Reason:  To protect the privacy and environment of people in proposed and neighbouring residential properties, in accordance with the National Planning Policy Framework (2019), Core Strategy (2007) policy CP4, Development Management Document  (2015) policy DM1, and advice contained within the Design and Townscape Guide (2009).

 

 

 

05       The hard and soft landscaping and boundary treatments at the site shall be carried out in full accordance with the proposed landscaping scheme including street tree planting as shown on plans ref 385-P703A and GBU 2113  prior to occupation of the dwellings hereby approved. Any trees or shrubs dying, removed, being severely damaged or becoming seriously diseased within five years of planting shall be replaced with trees or shrubs of such size and species as may be agreed with the Local Planning Authority

 

Reason: In the interests of visual amenity of the area and the amenities of occupiers and to ensure a satisfactory standard of landscaping pursuant to Policy DM1 of the Development Management Document (2015)  and Policy CP4 of the Core Strategy (2007)

 

 

06       No drainage infrastructure associated with this development shall be undertaken until details of the design implementation; maintenance and management of a scheme for surface water drainage works (incorporating Sustainable Urban Drainage (SuDs) Principles) have been submitted to and approved by the local planning authority. The approved scheme shall be implemented,  in accordance with the approved details before the development is occupied or brought into use and shall be maintained as such thereafter in perpetuity.

 

Reason: To prevent flooding by ensuring the satisfactory storage and disposal of surface water from the site for the lifetime of the development and to prevent environmental and amenity problems arising from flooding in accordance with the National Planning Policy Framework (2019), Policy KP2 and CP4 of the Core Strategy (2007) and  Policy DM2 of the Development Management Document  (2015)

 

07       Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (as amended), or any Order or Act of Parliament revoking and re-enacting that Order with or without modification, no extensions or detached buildings shall be erected at the development hereby approved specified within Schedule 2, Part 1, Classes A, B, D, E and F of the Town and Country Planning (General Permitted Development) Order 2015 without the receipt of express planning permission in writing from the Local Planning Authority.

 

Reason:  To enable the Local Planning Authority to regulate and control development in the interest of the amenity of neighbouring properties and to safeguard the character of the area in accordance the National Planning Policy Framework (2019), Core Strategy (2007) Policies KP2 and CP4, Development Management Document (2015) Policy DM1 and the Southend Design and Townscape Guide (2009).

 

 

 

 

 

 

 

08       The eight car parking spaces and the associated vehicular accesses for the spaces to access the public highway, shown on approved plan 385-P703A shall be provided and made available for use at the site prior to the first occupation of the dwellings hereby approved. The car parking spaces and the associated vehicular accesses to and from the public highway shall thereafter be permanently retained solely for the parking of vehicles and the accessing of the car parking spaces in connection with the occupiers of the dwellings hereby approved and their visitors.

 

Reason: To ensure that satisfactory off-street car parking is provided in the interests of residential amenity and highways efficiency and safety, in accordance with the National Planning Policy Framework (2019), Core Strategy (2007) policy KP2, Development Management Document (2015) policy DM15 and the Southend Design and Townscape Guide (2009). 

 

 

09       The tree and tree root protection measures as set out in Section 4 of the submitted Arboricultural Impact Assessment by Owen Allpress reference 1874 dated 24th October 2019 and associated tree protection plan reference 1874-02-P1 in relation to the trees identified as T1-T10 in this statement shall be implemented in full prior to commencement of the development and be retained throughout the construction phase of the development. The mitigation measures in relation to construction within the root protection areas of the trees denoted as T8, T9 and T10 in the  Arboricultural Impact Assessment by Owen Allpress reference 1874 dated 24th October 2019 shall also be implemented in full during the construction works, including supervision of works by a qualified arboriculturalist. Implementation of the development shall be undertaken only in full accordance with British Standard 3998 and British Standard 5837.

 

Reason: A condition is justified to ensure the trees on and close to the site are adequately protected during building works in the interests of visual amenity and in accordance with Core Strategy (2007) policies KP2 and CP4, Development Management Document (2015) policy DM1 and advice contained within the Southend Design and Townscape Guide (2009).

 

 

10       Prior to the commencement of the development the following information shall be submitted to and approved in writing by the local planning authority:

 

i.         Full details of the proposed tree works to trees T8 and T9 as identified in the submitted Arboricultural Impact Assessment by Owen Allpress reference 1874 dated 24th October 2019.

ii.        Full design and construction details of the cellular confinement installation for the forecourt parking area including information on levels and the crossover referred to in the Arboricultural Impact Assessment by Owen Allpress reference 1874 dated 24th October 2019

 

The development shall then only be carried out in accordance with the approved details and shall be completed in accordance with the approved details before the development is first occupied. Implementation of the development shall be undertaken only in full accordance with British Standard 3998 and British Standard 5837.

 

Reason: A pre commencement condition is justified to ensure the trees on and close to the site are adequately protected during building works in the interests of visual amenity and in accordance with Core Strategy (2007) policies KP2 and CP4, Development Management Document (2015) policy DM1 and advice contained within the Southend Design and Townscape Guide (2009).

 

 

11       Prior to occupation of the dwellings hereby approved, appropriate water efficient design measures as set out in Policy DM2 (iv) of the Development Management Document to limit internal water consumption to not more than 105 litres per person per day (lpd) (110 lpd when including external  water  consumption), to include measures of water efficient fittings, appliances and water recycling systems such as grey water and rainwater harvesting shall be implemented for the development and thereafter retained in perpetuity.

 

Reason: To minimise the environmental impact of the development through efficient use of water in accordance with the National Planning Policy Framework (2019), Core Strategy (2007) Policy KP2, Development Management Document (2015) Policy DM2 and advice contained within the Southend Design and Townscape Guide (2009).

 

12       A scheme detailing how at least 10% of the total energy needs of the development will be supplied using on site renewable sources shall be submitted to, agreed in writing by the Local Planning Authority and implemented in full in accordance with the approved details prior to the first occupation of the dwellings hereby approved. This provision shall be made for the lifetime of the development.

 

Reason: To minimise the environmental impact of the development through efficient use of resources and better use of sustainable and renewable resources in accordance with the National Planning Policy Framework (2019), Core Strategy (2007) policy KP2 and CP4, Development Management Document (2015) policy DM2 and the Southend Design and Townscape Guide(2009).

 

 

13       The development hereby approved shall be carried out in a manner to ensure the dwellinghouses comply with building regulation M4 (2) ‘accessible and adaptable dwellings’ before they are occupied.

 

Reason: To ensure the residential units hereby approved provides a high quality and flexible internal layout to meet the changing needs of residents in accordance with National Planning Policy Framework (2019), Core Strategy (2007) policy KP2, Development Management Document (2015) policy DM8 and the advice contained in the Southend Design and Townscape Guide (2009).

 

14       Prior to the commencement of development, a full Phase 1 Habitat Survey of this site including a more in depth survey of badger activity and camera traps surveys, a scheme of any relevant biodiversity or wildlife mitigation measures to be implemented in association with the development and a timescale for their implementation shall be submitted to and approved in writing by the local planning authority. Any mitigation measures set out in the agreed report shall be implemented and completed in full in accordance with the agreed timetable.

 

Reason: A pre commencement condition is justified to ensure any protected species and habitats utilising the site are adequately protected during building works in accordance with the National Planning Policy Framework (2019), Core Strategy (2007) policy KP2, Development Management Document (2015) policy DM2.

 

15       No development shall take place, including any works of demolition, until a Construction Method Statement has been submitted to, and approved in writing by, the local planning authority. The approved Statement shall be adhered to in full throughout the construction period. The Statement shall provide, amongst other things, for:

 

i)  the parking of vehicles of site operatives and visitors

ii)  loading and unloading of plant and materials

iii)  storage of plant and materials used in constructing the development

iv)  measures to control the emission of dust and dirt during construction

v)  a scheme for recycling/disposing of waste resulting from demolition and construction works that does not allow for the burning of waste on site.

vi) a detailed timetable for the supervision of works by a qualified arboriculturalist.

vii) noise mitigation measures to be used during construction.

 

Reason: A pre commencement condition is justified in the interests of visual amenity and the amenities of neighbours pursuant to Policy CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015).

 

 

16       Construction Hours for the development hereby approved shall be restricted to 8am – 6pm Monday to Friday, 8am - 1pm Saturday and not at all on Sundays or Bank Holidays.

 

Reason: In the interests of visual amenity and the amenities of neighbours and to ensure a satisfactory standard of landscaping pursuant to Policy CP4 of the Core Strategy (2007) and Policies DM1 and DM3 of the Development Management Document (2015).

 

 

 

 

 

 

 

 

17       Notwithstanding the details submitted and otherwise hereby approved, no development shall be undertaken unless and until full details of the existing and proposed levels to include the proposed dwellings, forecourts and landscaped areas relative to the adjoining land and any other changes proposed in the existing levels of the site have been submitted to and approved in writing by the local planning authority. The development shall thereafter be implemented and completed only in accordance with the approved details.

 

Reason: A pre commencement condition is required to safeguard the visual amenities of the site and wider area as set out in Core Strategy (2007) Policies KP2 and CP4, Development Management Document (2015) Policies DM1 and DM3 and the advice contained within the Southend Design and Townscape Guide (2009).

 

Informatives:

 

01       Please note that the development the subject of this application is liable for a charge under the Community Infrastructure Levy (CIL) Regulations 2010 (as amended) and it is the responsibility of the landowner(s) to ensure they have fully complied with the requirements of these regulations. A failure to comply with the CIL regulations in full can result in a range of penalties. For full planning permissions, a CIL Liability Notice will be issued by the Council as soon as practicable following this decision notice. For general consents, you are required to submit a Notice of Chargeable Development (Form 5) before commencement; and upon receipt of this, the Council will issue a CIL Liability Notice including details of the chargeable amount and when this is payable. If you have not received a CIL Liability Notice by the time you intend to commence development it is imperative that you contact S106andCILAdministration@southend.gov.uk to avoid financial penalties for potential failure to comply with the CIL Regulations 2010 (as amended).

 

02       You should be aware that in cases where damage occurs during construction works to the highway in implementing this permission that Council may seek to recover the cost of repairing public highways and footpaths from any party responsible for damaging them. This includes damage carried out when implementing a planning permission or other works to buildings or land. Please take care when carrying out works on or near the public highways and footpaths in the Borough.

 

 

03       The applicant is reminded that they are required to adhere to the Conservation (Natural Habitats &c.) (Amendment) Regulations 2007 and the Wildlife and Countryside Act (1981) in relation to development works close to protected species including badgers and bats. A Protected Species Licence may be required. 

 

The Local Planning Authority has acted positively and proactively in determining this application by identifying matters of concern within the application (as originally submitted) and negotiating, with the Applicant, acceptable amendments to the proposal to address those concerns.  As a result, the Local Planning Authority has been able to grant planning permission for an acceptable proposal, in accordance with the presumption in favour of sustainable development, as set out within the National Planning Policy Framework.  The detailed analysis is set out in a report on the application prepared by officers.

 

Supporting documents:

 

Get the best from this site

We use simple text files called 'cookies'. Some of these cookies are essential to make our site work and others help us to improve by giving us some insight into how the site is being used. For more information, including how to turn cookies off, see more about cookies - or simply click the Continue button to use this site as normal.